North America Industrial Construction Cost Guide 2023
Construction Timelines: Cushman & Wakefield’s construction contractor sentiment survey indicates that material lead times and project execution timelines continued to increase in the last six months. Of contractors responding, 44% believe that lead times had remained constant (38%) or decreased slightly (6%); the remaining 56% of respondents believe lead times increased slightly (38%) or significantly (19%) over the previous six months. Project execution delays have been more challenged. Only 9% didn’t experience increases while 86% saw slight (69%) to significant (19) increases. A recent report from Associated Builders and Contractors points to project backlog increases in commercial construction 2 . As of November 2022, the backlog increased to 9.1 months, the highest level since 2019 Q2, indicating that timelines will remain constrained. Large commercial projects have been a major contributor to backlog increases.
KEY TAKEAWAY Construction contractors expect increased challenges in project execution timelines and material lead times. The vast majority (85%) expect slight (66%) to significant (19%) increases in material lead times. This is marginally more optimistic than sentiment from a year ago when 88% of GCs expected material lead times to increase slightly (36%) to significantly (52%). While the industry may see material lead times easing, significant issues remain with electrical gear and regionally with core materials, such as cement and sand.
2 Commercial, Institutional and Health Care Construction Drive ABC’s Backlog Indicator to Highest Level Since Q2 2019”; Associated Builders and Contractors; https://www.abc. org/News-Media/News-Releases/entryid/19722/commercial-institutional-and-health care-construction-drive-abcs-backlog-indicator-to-highest-level-since-q2-2019; accessed December 16, 2022.
LEAD AND EXECUTIONS TIMES ARE EXPECTED TO CONTINUE TO INCREASE Cushman & Wakefield Construction Contractor Sentiment Survey, December 2022
Decreased Slightly Increased Slightly
No Change
Increased Significantly
100%
19%
19%
19%
22%
80%
38%
60%
66%
69%
72%
40%
38%
20%
6% 9%
3% 9%
3%
6%
0%
Material Lead Times
Project Execution Time
Material Lead Times
Project Execution Time
Past 6 Months
Next 6 Months
Source: Cushman & Wakefield Research
6 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023