North America Industrial Construction Cost Guide 2023
Animated publication
INDUSTRIAL CONSTRUCTION COST GUIDE 2023 NORTH AMERICA
INTRODUCTION Construction activity in the industrial sector has raced to keep up with robust demand of the last two years in North American markets. While industrial construction pipelines continue at historically high levels, the sector is facing several headwinds. Pandemic-related supply chain constraints, which helped drive commodities costs up, continue to have a lingering impact on overall costs and material lead times. A significantly higher interest rate environment in the United States provides additional upward pressure to costs. The fed rate is currently 4.25%-4.5% up from nearly zero in March 2022. As the sector faces a potential cooling down in 2023, we are closely monitoring the costs and material lead times which could allow projects more flexibility in their delivery timelines.
43 MARKETS IN NORTH AMERICA
The Guide includes comprehensive construction costs including all relevant trade codes, general conditions, fees and contingency. The Guide specifically excludes FF&E, IT, audio/visual, and security cost for the office component and soft costs or purchase of land for the overall industrial project.
2 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
C U S H M A N & WA K E F I E L D
KEY TAKEAWAY • Steel prices remain elevated at a 20% increase year-over year (YoY). Prices are forecast to drop slightly and level out over the next couple of years. • After reaching peak levels in 2021 Q2, lumber pricing has moderated, registering a 6% increase YoY. Pricing is forecast to level out but remain above pre-pandemic levels for the next few years. • Copper prices have faced significant volatility, but after hitting a peak at the beginning of this year, 2022 Q1, they have fallen 16% on a YoY basis. A modest drop in prices is forecast for 2023.
ECONOMIC OVERVIEW Strong demand for industrial properties, fueled in great part by the rise in e-commerce, has led to historic levels of construction in the sector. Competition for materials in a commodity constrained market, coupled with inflationary pressures, has driven construction costs higher across all real estate sectors. Commodities Pricing Update: Pandemic related supply chain constraints, which led to elevated commodities pricing, have begun to ease. Bottlenecks of container ships at ports are no longer the norm. According to FreightWaves, North American container ship traffic on November 23rd was down 60% from recent highs. Only 59 container ships were waiting for a berth. However, this was still above pre-pandemic levels, which were typically in single digits. The easing of traffic at ports may signal forthcoming easing of materials availability. That said, due to continued pent up demand, costs have not fallen to pre-pandemic levels. Concrete pricing has increased 14% from Q3 2021 and is currently at its peak pricing and YoY growth. Though pricing is unlikely to fall, the rate of growth will slow to more moderate levels in the next couple years.
COMMODITY PRICE INCREASES MODERATING Cost Index for Lumber, Steel and Copper
Forecast
Lumber
Steel (Pipe and Tube)
Copper
800
700
-16% decrease YOY
20% increase YOY
600
500
400
300
Cost Index
6% increase YOY
200
100
0
Source: U.S. Bureau of Labor Statistics (BLS); Moody’s Analytics Forecasted
3
CUSHMAN & WAKEFIELD
C U S H M A N & WA K E F I E L D
KEY TAKEAWAY Despite slower rate of cost contractor sentiment survey 1 , GCs generally expect costs to continue to increase in the next six months. 65% of GCs expect their costs to increase slightly (63%) to significantly (6%), while 76% expect their supplier prices to increase slightly (63%) to significantly (13%). This sentiment is more optimistic than a year ago when 96% of GCs expected their supplier prices to increase slightly (64%) to significantly (32%). escalation, according to the Cushman & Wakefield
Building Costs Moderate: Easing in materials pricing has led to slower increases of building costs. The annual change in the ENR building cost index was still elevated at 11.4% in 2022 Q3, though down from 15.4% the previous quarter. Building costs are forecast to ease next year and level out in the longer term. However, an influx of capital from the federal Infrastructure Investment and Jobs Act, the CHIPS Act and the Inflation Reduction Act will fuel continued construction growth in the near term, potentially delaying a return to pre-pandemic pricing. • A component of the ENR building cost index is skilled labor, which includes union wages plus fringe benefits for carpenters, bricklayers and iron workers. Skilled labor costs grew 3.5% YoY, their largest annual increase in 10 years, illustrating labor constraints and inflationary impact on wages. • Another important consideration in the coming quarters will be construction financing. In the current climate, it has become increasingly difficult to finance new projects. While this won’t necessarily impact projects already underway, it could have a dampening impact on the longer-term pipeline.
1 During the fall of 2022, Cushman & Wakefield surveyed over 50 general contractors across North America focusing on industrial projects. The survey gauged their sentiment on topics related to costs, labor and material lead times, among others.
CONTRACTORS AND SUPPLIERS ANTICIPATE RISING PRICES Cushman & Wakefield Construction Contractor Sentiment Survey, December 2022
Decreased Slightly Increased Slightly
No Change
Increased Significantly
100%
6%
13%
16%
80%
44%
63%
60%
63%
63%
40%
41%
20%
25%
19%
16%
13%
6%
6%
0%
General Contractors
GC's Subs & Suppliers
General Contractors
GC's Subs & Suppliers
Past 6 Months
Next 6 Months
2 https://www2.deloitte.com/content/dam/Deloitte/global/Documents/About-Deloitte/deloitte-2019 millennialsurvey.pdf
Source: Cushman & Wakefield Research
4 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
NEW CONSTRUCTION STARTS ACCELERATED THROUGH 2022 Value of New Construction Starts: Non-Residential Buildings, 12-Month Trailing Average
$125,000 $150,000 $175,000 $200,000 $225,000 $250,000 $275,000 $300,000 $325,000 $350,000 $375,000 $400,000 Millions USD, SAAR
Non-residential building starts declined 19.9% from February 2020 to April 2021.However, industrial starts did not decline over this period. As of September 2022, non-residential starts rose 32.7% year-over year.
Source: Dodge Data & Analytics: New Construction Starts Report
KEY TAKEAWAY • Labor constraints will continue to impact construction employment in the near-term. An increase in retirements due to an aging workforce, coupled with a lack of young workers from the overall talent pool is impacting wages and costs as well as project timelines. The introduction of skills-based programs for young workers in addition to competitive wages may help fill the talent gap in the coming years. A recent survey by The Associated General Contractors of America (AGC) found that 70% of respondent firms plan to increase headcount in 2023, however, over 80% are having difficulty filling open positions. Additionally, the AGC survey indicates that companies will increase pay (72% of respondent firms), provide incentives and bonuses and increase their corresponding payment of benefit packages to retain and attract talent.
Employment and Construction: Non-residential new construction starts accelerated in 2022. After slowing from February to April 2021, starts accelerated and peaked in September 2022 at a 32.7% increase on a YoY basis. While increased materials costs did not slow starts in 2022, the addition of accelerated interest rate increases on financing could slow the growth as costs are compounded. • U.S. construction employment grew 3.8% YoY basis in 2022 Q3. Wages in the construction sector have risen at a faster pace in order to attract talent in a labor constrained market. On a YoY basis, wages grew 11.4% in 2022 Q3. • Canadian construction employment grew nearly 6.0% YoY as of 2022 Q2, while wages grew 3.5% YoY. Wage growth have been more moderated in Canada. However, inflationary pressures may impact near-term wage growth.
5
CUSHMAN & WAKEFIELD
Construction Timelines: Cushman & Wakefield’s construction contractor sentiment survey indicates that material lead times and project execution timelines continued to increase in the last six months. Of contractors responding, 44% believe that lead times had remained constant (38%) or decreased slightly (6%); the remaining 56% of respondents believe lead times increased slightly (38%) or significantly (19%) over the previous six months. Project execution delays have been more challenged. Only 9% didn’t experience increases while 86% saw slight (69%) to significant (19) increases. A recent report from Associated Builders and Contractors points to project backlog increases in commercial construction 2 . As of November 2022, the backlog increased to 9.1 months, the highest level since 2019 Q2, indicating that timelines will remain constrained. Large commercial projects have been a major contributor to backlog increases.
KEY TAKEAWAY Construction contractors expect increased challenges in project execution timelines and material lead times. The vast majority (85%) expect slight (66%) to significant (19%) increases in material lead times. This is marginally more optimistic than sentiment from a year ago when 88% of GCs expected material lead times to increase slightly (36%) to significantly (52%). While the industry may see material lead times easing, significant issues remain with electrical gear and regionally with core materials, such as cement and sand.
2 Commercial, Institutional and Health Care Construction Drive ABC’s Backlog Indicator to Highest Level Since Q2 2019”; Associated Builders and Contractors; https://www.abc. org/News-Media/News-Releases/entryid/19722/commercial-institutional-and-health care-construction-drive-abcs-backlog-indicator-to-highest-level-since-q2-2019; accessed December 16, 2022.
LEAD AND EXECUTIONS TIMES ARE EXPECTED TO CONTINUE TO INCREASE Cushman & Wakefield Construction Contractor Sentiment Survey, December 2022
Decreased Slightly Increased Slightly
No Change
Increased Significantly
100%
19%
19%
19%
22%
80%
38%
60%
66%
69%
72%
40%
38%
20%
6% 9%
3% 9%
3%
6%
0%
Material Lead Times
Project Execution Time
Material Lead Times
Project Execution Time
Past 6 Months
Next 6 Months
Source: Cushman & Wakefield Research
6 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
C U S H M A N & WA K E F I E L D
INDUSTRIAL MARKET UPDATE Growth in Industrial Demand: The industrial sector has been among the winners in the wake of the pandemic. Skyrocketing e-commerce demand—along with focus on improved supply chains and increased interest in manufacturing onshore—has driven North American industrial demand over the past three years. In the U.S. alone, over 1.3 billion square feet (bsf) was absorbed between 2020 and the end of 2022. That is 56% higher than the next best three-year period (2017-2019) and is 100 msf larger than all of the industrial space in the Americas’ largest market, Chicago. Looking forward, e-commerce demand may be easing but retail, manufacturing, battery manufacturing and storage, semiconductor manufacturing and specialty use demand is replacing it.
KEY TAKEAWAY Record demand has driven sub-4% vacancy rates across the region. As of Q4 2022, the national Canadian vacancy rate was 1.4%, the U.S. 3.3%, and both Mexico City and Monterrey, Mexico were below 3%. As vacancy has grown tighter industrial asking rents have increased. In Q4 2022, U.S. asking rents were up 18.6% YoY and up 38% since the beginning of the pandemic. Canadian asking rents have increased even more substantially: up 45% YoY and 81% since Q4 2019. Latin American rents are down from pre-pandemic highs but have increased by 12% YoY.
STRONGEST 3-YEAR PERIODS OF NET ABSORPTION (MSF)
#1 1,336 MSF
600
500
400
#2 854 MSF
#4 721 MSF
#5 684 MSF
#3 838 MSF
300
200
100
0
Source: Cushman & Wakefield Research
7
CUSHMAN & WAKEFIELD
Record Level of Construction: New supply has not been able to keep up with industrial demand, but certainly not for lack of trying. Since the beginning of the pandemic, over 2.1 bsf of industrial space has been delivered across the globe. The Americas has accounted for 62% of that new construction—1.2 bsf in the U.S., 68.4 msf in Canada and 34 msf in Latin America. Additionally, a record level of industrial space under construction remains. The 731 msf of space under construction in the Americas represents 4.0% of current industrial inventory in the region.
INDUSTRIAL DELIVERIES DURING THE PANDEMIC, BY QUARTER
KEY TAKEAWAY Project costs and timelines continue to be impacted by record levels of industrial construction. Even as the pandemic’s negative impact on supply chains lessens, materials and labor challenges remain, making it difficult for developers, landlords and occupiers to complete industrial projects on time and on budget. Given recent occupier demand, a significant slowdown in the construction pipeline is not likely anytime soon.
APAC LATAM Greater China Canada EMEA United States
250
200
150
MSF
100
50
0
Q1 2021
Q2 2021
Q1 2022
Q3 2021
Q4 2021
Q1 2020
Q2 2022
Q3 2022
Q4 2022
Q2 2020
Q3 2020
Q4 2020
*Q4 2022 data not available for other regions at time of publication. Source: Cushman & Wakefield Research
8 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
C U S H M A N & WA K E F I E L D
KEY TAKEAWAY The pipeline remains strong, with over 230 msf of industrial space currently under construction in the five markets with the largest pipeline. Five U.S. Sunbelt markets have construction pipelines above 10% of current inventory: Phoenix, Savannah, Las Vegas, Charleston, Austin and Fredericksburg. Outside of the U.S., Toronto has the most construction activity (21 msf) while Mexico City, Vancouver and Calgary each have between 8 and 9 msf under construction. The two Mexico markets Cushman & Wakefield tracks—Mexico City and Monterrey—and three Canadian markets— Calgary, Vancouver and London—have construction pipelines that amount to over 3.0% of current inventory.
ABSOLUTE BASIS: COMPLETIONS SINCE BEGINNING OF PANDEMIC (Q1 2020-Q4 2022)
Las Vegas Louisville Charlotte Central Valley CA
West South Northeast Midwest Latin America Canada
Mexico City Philadelphia Denver Salt Lake City Nashville
Dallas/Ft. Worth Houston Atlanta Chicago PA I-81/I-78 Corridor Phoenix Inland Empire Indianapolis Toronto Memphis Columbus Savannah Sao Paulo Kansas City New Jersey - Central
Construction Activity in Key Markets: Construction activity has been broad based as demand for additional space has been strong across the region. Since the beginning of 2020, eight different markets have seen more than 50 msf of new construction delivered and 19 markets have seen more than 20 msf. This is led by large U.S. Sunbelt markets—Dallas/Ft. Worth, Atlanta and Houston—and major Midwest industrial hubs—Chicago and Indianapolis. Outside the U.S., recent deliveries have been largest in Sao Paulo (27 msf) and Toronto (34 msf). On a percentage basis, smaller Sunbelt markets have led the way. More than a fifth of current inventory has been delivered in the past three years in Birmingham, Savannah and Austin. Already large industrial hub markets have added approximately 15% of inventory: Pennsylvania I-81/I-78 Distribution Corridor (18%), Indianapolis (16%), Phoenix (115%) and Houston (14%).
0
20 40 60 80
MSF
*Latin America as of Q3 2022 Source: Cushman & Wakefield Research
SHARE OF INVENTORY: COMPLETIONS SINCE BEGINNING OF PANDEMIC (Q1 2020-Q4 2022)
Total Completions Since 2020 Share of Inventory (rhs)
10% 15% 20% 25% 30% 35% 40%
20 30 40 50 60 70 80 90
MSF
0% 5%
0 10
Share of Current Inventory
Boise
Birmingham Savannah Austin
Tampa
Louisville Atlanta
Phoenix
Houston
Philadelphia Memphis
Columbus
Las Vegas
Charleston
Indianapolis
Fredericksburg Salt Lake City
Colorado Springs
Central Valley CA
Palm Beach County
Source: Cushman & Wakefield Research
9
CUSHMAN & WAKEFIELD
C U S H M A N & WA K E F I E L D
KEY TAKEAWAY Even with all of the aforementioned construction likely outpacing tenant demand over the next few years, vacancy rates are expected to stay near historical lows. National U.S. vacancy is forecast to increase by 100-130 basis points in 2023, still a healthy level for the U.S. market.
National and Market Vacancy Rates: The majority of North American industrial markets currently have vacancy rates below 5.0%, including 73 U.S. markets, 11 Canadian markets and both markets in Mexico. In most cases, vacancies are considerably tighter than was experienced during the 2000s expansion. In fact, even if all of the space currently under construction (731 msf) across the Americas were to deliver without any of it being leased, region-wide vacancy would remain below 7.0%, and North American vacancy (U.S. & Canada) would still be 7.2%. • The ongoing tight market conditions and competition for space saw another quarter of rent growth in Q4 2022, increasing 18.6% YoY. At $8.81 per square foot (psf), Q4 2022 is the third quarter to eclipse $8.00 psf in U.S. industrial history. Asking rental rate growth will persist going forward. However, growth rates are projected to moderate compared to the double-digit growth rates observed in recent quarters as the pipeline brings more space to the market. There will be a flight to the quality space that comes online.
CURRENTLY UNDER CONSTRUCTION Markets with largest amount of square footage under construction (as of Q4 2022)
Under Construction UC as % of Inventory
20 30 40 50 60 70 80
12% 15% 18% 21% 24%
MSF
0% 3% 6% 9%
0 10
*Mexico as of Q3 2022 Source: Cushman & Wakefield Research
10 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
VACANCY RATES REMAIN BELOW PREVIOUS LOWS Select markets, U.S. & Canada
Q4 2022 Prior Cycle Lows (2002-2007)
12%
10%
8%
6%
4%
2%
0%
Source: Cushman & Wakefield
11
AMERICAS OFFICE FIT-OUT COST GUIDE 202 2
CUSHMAN & WAKEFIELD
INDUSTRIAL COST COMPARISONS
USING THE GUIDE
Estimated costs provided herein are indicative of market averages based on certain assumptions. Exact costs for specific projects may differ to those presented here, and so we recommend engaging a Cushman & Wakefield Project & Development Services professional to advise on precise costings based on your unique construction requirements.
12 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
MOSTEXPENSIVE AND COST-EFFECTIVE MARKETS
North American costs for industrial properties averaged $84 psf for medium size projects (476,400 sf) and $79 psf for large size projects (901,000 sf).
> The priciest markets are located in Western U.S. and Canada. Of the top six most expensive markets, four are located on the West Coast and two are located in Canada. The most expensive market is Portland, where costs for medium size projects average $105 psf and large size projects average $98 psf. Portland Medium - $105 psf Large - $98 psf Calgary Medium - $101 psf Large - $98 psf San Diego Medium - $101 psf Large - $92 psf Seattle Medium - $100 psf Large - $92 psf Oakland Medium - $100 psf Large - $93 psf M ontreal Medium - $97 psf Large - $93 psf
• Memphis • Mexico City • Guadalajara • Nashville • Louisville
> The most cost-effective markets include a mix of markets in Mexico and the
midwestern and southern U.S.
13
CUSHMAN & WAKEFIELD
BREAKDOWN OF EXPENSES BY CATEGORY
Costs are broken out into six major categories: Site Work; Base Building Structural & Enclosure; Base Building Architectural; Base Building MEP; GC’s and GR’s & Fee; and Contingency
25%
24%
17%
Site work accounts for 17% of total costs across all markets and project size.
Across all markets and project sizes, the structural (slab on grade and structural framing system) is the largest category of fit-out costs, accounting for 25% of the total .
The second highest cost category is building enclosure (exterior wall, exterior panels, windows, roofing, exteriors doors, etc.) at 24% of total for both medium and large projects.
14 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
PDS AMERICAS COST GUIDE – PRICING CRITERIA METHODOLOGY • The industrial build-to-suit project data is based on modern-day distribution centers for two different sizes (476,400 RSF and 901,000 RSF). Office and other ancillary spaces customary in a distribution facility are included. The intended construction of the building is either precast insulated panels or tilt-up concrete panels with steel frame. The roof is a Thermoplastic Polyolefin (TPO) roof pitched to overflow scuppers for drainage. Floors are 8” thick slab with reinforced 4,000 psi concrete. Each building size has appropriate quantities of dock doors, levelers and drive-in ramps and overhead door. The office area is constructed with basic finishes excluding Furniture, Fixtures or Equipment (FF&E) and low voltage cabling, security or audio/visual equipment and systems. The office area is fully conditioned space with the warehouse unconditioned. Warehouse includes LED high-bay lighting.
• Allowances for site concrete, paving, landscaping, storm retention and site utilities are included. The pricing does not include soft costs or purchase of land. • Given the fluidity of the construction market, a ten percent (10%) contingency allowance has been included in the cost. • Costs in this guide were compiled from responses to a survey of general contractors (GCs) focused on industrial properties. 50 GCs representing 43 North American markets responded to the survey.
DISTRIBUTION CENTER COSTS Mediumand Large Projects byMarket
Medium (476,400 RSF)
Large (901,000 RSF)
$20 $30 $40 $50 $60 $70 $80 $90 $100 $110
$- $10
Houston Miami
Dallas
San Diego Seattle
Cincinnati Detroit
Vancouver Denver
Minneapolis Atlanta
Calgary
Phoenix
Toronto
Chicago
Oakland
Penn Corridor Monterrey St. Louis
Portland
Montreal
Mexico City Memphis
Nashville
Salt Lake
Charlotte
Louisville
Baltimore
Cleveland
Indianapolis Columbus
Greenville
Pittsburgh
Milwaukee
Orange Co.
New Jersey
Kansas City
Greensboro
Guadalajara
Los Angeles
Philadelphia
Inland Empire
Central Valley, CA
Source: Cushman & Wakefield Project & Development Services
15
CUSHMAN & WAKEFIELD
COSTSBYSEGMENT ANDMARKET MEDIUM PROJECTS (476,400 RSF)
United States
SEGMENT COST BY MARKET (MEDIUM PROJECTS)
$0
$50
$100
Portland San Diego Seattle Oakland Central Valley, CA Denver Phoenix Salt Lake
Los Angeles Greensboro Greenville Houston Miami Charlotte Orange Co. Dallas Inland Empire Chicago Cleveland Pittsburgh Minneapolis Atlanta New Jersey Philadelphia Indianapolis Columbus Milwaukee Penn Corridor St. Louis Cincinnati Detroit Kansas City
Site Work Base Bldg Structural & Enclosure Base Building Architectural Base Bldg MEP GC’s and GR’s & Fee Contingency
Baltimore Louisville Nashville Memphis
Source: Cushman & Wakefield Project & Development Services
16 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
SEGMENT COST COMPOSITION BY MARKET (MEDIUM PROJECTS) 0% 20% 40% 60%
80% 100%
Portland San Diego Seattle Oakland Central Valley, CA Denver Phoenix Salt Lake
Los Angeles Greensboro Greenville Houston Miami Charlotte Orange Co. Dallas Inland Empire Chicago Cleveland Pittsburgh Minneapolis Atlanta New Jersey Philadelphia Indianapolis Columbus Milwaukee Penn Corridor St. Louis Cincinnati Detroit Kansas City
Site Work Base Bldg Structural & Enclosure Base Building Architectural Base Bldg MEP GC’s and GR’s & Fee Contingency
Baltimore Louisville Nashville Memphis
Source: Cushman & Wakefield Project & Development Services
17
CUSHMAN & WAKEFIELD
COSTSBYSEGMENT ANDMARKET United States LARGE PROJECTS (901,000 RSF)
SEGMENT COST BY MARKET (LARGE PROJECTS)
$0
$50
$100
Portland Oakland Seattle San Diego Denver Phoenix Salt Lake Central Valley, CA Dallas Houston
Los Angeles Greensboro Greenville Orange Co. Charlotte Miami Inland Empire Cleveland Indianapolis Chicago Atlanta Columbus Minneapolis Cincinnati Milwaukee Pitt Louisville St. Louis Detroit Kansas City Nashville NJ Phily Baltimore Penn Corridor Memphis
Site Work Base Bldg Structural & Enclosure Base Building Architectural Base Bldg MEP GC’s and GR’s & Fee Contingency
Source: Cushman & Wakefield Project & Development Services
18 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
SEGMENT COST COMPOSITION BY MARKET (LARGE PROJECTS)
0% 20% 40% 60% 80% 100%
Portland Oakland Seattle San Diego Denver Phoenix Salt Lake Central Valley, CA Dallas Houston
Los Angeles Greensboro Greenville Orange Co. Charlotte Miami Inland Empire Cleveland Indianapolis Chicago Atlanta Columbus Minneapolis Cincinnati Milwaukee Pitt Louisville St. Louis Detroit Kansas City Nashville NJ Phily Baltimore Penn Corridor Memphis
Site Work Base Bldg Structural & Enclosure Base Building Architectural Base Bldg MEP GC’s and GR’s & Fee Contingency
Source: Cushman & Wakefield Project & Development Services
19
CUSHMAN & WAKEFIELD
COSTSBYSEGMENT ANDMARKET Canada (USD) MEDIUM PROJECTS (476,400 RSF)
SEGMENT COST BY MARKET
$0
$20 $40 $60 $80 $100 $120
Calgary
Montreal
Vancouver
Toronto
SEGMENT COST COMPOSITION BY MARKET
0%
20%
40%
60%
80% 100%
Calgary
Montreal
Vancouver
Site Work Base Bldg Structural & Enclosure Base Building Architectural Base Bldg MEP GC’s and GR’s & Fee Contingency
Toronto
Source: Cushman & Wakefield Project & Development Services
20 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
COSTSBYSEGMENT ANDMARKET Canada (USD) LARGE PROJECTS (901,000 RSF)
SEGMENT COST BY MARKET
$0
$20 $40 $60 $80 $100 $120
Calgary
Montreal
Vancouver
Toronto
SEGMENT COST COMPOSITION BY MARKET
0%
20%
40%
60%
80% 100%
Calgary
Montreal
Site Work Base Bldg Structural & Enclosure Base Building Architectural Base Bldg MEP GC’s and GR’s & Fee Contingency
Vancouver
Toronto
Source: Cushman & Wakefield Project & Development Services
21
CUSHMAN & WAKEFIELD
COSTSBYSEGMENT ANDMARKET Mexico (USD) MEDIUM PROJECTS (476,400 RSF)
SEGMENT COST BY MARKET
$0
$20
$40
$60
$80
$100
Monterrey
Guadalajara
Mexico City
SEGMENT COST COMPOSITION BY MARKET
0%
20%
40%
60%
80% 100%
Monterrey
Guadalajara
Site Work Base Bldg Structural & Enclosure Base Building Architectural Base Bldg MEP GC’s and GR’s & Fee Contingency
Mexico City
Source: Cushman & Wakefield Project & Development Services
22 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
COSTSBYSEGMENT ANDMARKET Mexico (USD) LARGE PROJECTS (901,000 RSF)
SEGMENT COST BY MARKET
$0
$20
$40
$60
$80
Monterrey
Guadalajara
Mexico City
SEGMENT COST COMPOSITION BY MARKET
0%
20%
40%
60%
80% 100%
Monterrey
Guadalajara
Site Work Base Bldg Structural & Enclosure Base Building Architectural Base Bldg MEP GC’s and GR’s & Fee Contingency
Mexico City
Source: Cushman & Wakefield Project & Development Services
23
CUSHMAN & WAKEFIELD
24 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
COSTSBYMARKET
MEDIUM PROJECTS (476,400 RSF): ALL MARKETS
Northeast US Eastern US Midwest US Southeast US Southwest US Western US Canada Mexico
$225
$200
$175
$150
$125
$100
$75
$50
$25
$0
LARGE PROJECTS (901,000 RSF): ALL MARKETS
Northeast US Eastern US Midwest US Southeast US Southwest US Western US Canada Mexico
$225
$200
$175
$150
$125
$100
$75
$50
$25
$0
Source: Cushman & Wakefield Project & Development Services
25
CUSHMAN & WAKEFIELD
LOCALMARKETDATA
ATLANTA
BALTIMORE
Medium Large
Medium Large
$12.18
$11.55
$16.91
$13.81
Site Work
Site Work
$42.30
$38.57
$36.14
$33.64
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$5.12
$6.76
$5.83
$6.07
Base Bldg Architectural
Base Bldg Architectural
$5.71
$5.27
$7.48
$7.17
Base Bldg MEP
Base Bldg MEP
$6.90
$5.71
$2.88
$1.88
GC's and GR's & Fee
GC's and GR's & Fee
$6.83
$6.42
$6.76
$6.15
Contingency
Contingency
$79.03
$74.27
$75.99
$68.72
Total Cost
Total Cost
CENTRAL VALLEY, CA
CHARLOTTE
Medium Large
Medium Large
$12.59
$10.69
$16.77
$15.02
Site Work
Site Work
$53.34
$50.49
$42.47
$37.88
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$5.01
$6.27
$5.35
$6.98
Base Bldg Architectural
Base Bldg Architectural
$6.45
$5.20
$7.07
$6.76
Base Bldg MEP
Base Bldg MEP
$8.53
$7.07
$7.59
$6.79
GC's and GR's & Fee
GC's and GR's & Fee
$7.96
$7.38
$7.39
$6.87
Contingency
Contingency
$93.88
$87.10
$86.63
$80.31
Total Cost
Total Cost
CHICAGO
CINCINNATI
Medium Large
Medium Large
$12.97
$12.40
$15.98
$13.03
Site Work
Site Work
$44.77
$40.59
$35.27
$34.48
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$5.13
$6.11
$4.87
$6.27
Base Bldg Architectural
Base Bldg Architectural
$7.10
$6.10
$9.10
$8.78
Base Bldg MEP
Base Bldg MEP
$5.53
$4.48
$4.88
$3.61
GC's and GR's & Fee
GC's and GR's & Fee
$7.27
$6.74
$6.71
$6.40
Contingency
Contingency
$82.77
$76.42
$76.81
$72.55
Total Cost
Total Cost
NOTES: 1. Medium (476,400 RSF) 2. Large (901,000 RSF) 3. All costs in USD; conversions made using 2022 rates
26 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
LOCALMARKETDATA
CLEVELAND
COLUMBUS
Medium Large
Medium Large
$16.94
$13.81
$16.30
$13.29
Site Work
Site Work
$37.38
$36.55
$35.97
$35.17
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$5.16
$6.65
$4.97
$6.40
Base Bldg Architectural
Base Bldg Architectural
$9.65
$9.30
$9.28
$8.95
Base Bldg MEP
Base Bldg MEP
$5.17
$3.83
$4.97
$3.68
GC's and GR's & Fee
GC's and GR's & Fee
$7.11
$6.78
$6.84
$6.52
Contingency
Contingency
$81.41
$76.91
$78.34
$74.01
Total Cost
Total Cost
DALLAS
DENVER
Medium Large
Medium Large
$14.48
$15.53
$17.09
$19.85
Site Work
Site Work
$49.80
$46.61
$40.47
$32.31
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$3.55
$5.91
$18.29
$22.19
Base Bldg Architectural
Base Bldg Architectural
$6.33
$5.76
$4.75
$4.46
Base Bldg MEP
Base Bldg MEP
$4.12
$3.54
$2.81
$2.62
GC's and GR's & Fee
GC's and GR's & Fee
$7.50
$7.44
$8.20
$7.96
Contingency
Contingency
$85.79
$84.80
$91.61
$89.40
Total Cost
Total Cost
DETROIT
GREENSBORO
Medium Large
Medium Large
$11.93
$11.41
$17.06
$15.21
Site Work
Site Work
$41.19
$37.34
$43.15
$38.06
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$4.72
$5.62
$5.35
$6.98
Base Bldg Architectural
Base Bldg Architectural
$6.54
$5.61
$7.07
$6.76
Base Bldg MEP
Base Bldg MEP
$5.09
$4.12
$7.64
$6.73
GC's and GR's & Fee
GC's and GR's & Fee
$6.68
$6.20
$7.50
$6.90
Contingency
Contingency
$76.15
$70.31
$87.78
$80.64
Total Cost
Total Cost
NOTES: 1. Medium (476,400 RSF) 2. Large (901,000 RSF) 3. All costs in USD; conversions made using 2022 rates
27
CUSHMAN & WAKEFIELD
LOCALMARKETDATA
HOUSTON
GREENVILLE
Medium Large
Medium Large
$14.24
$15.27
$16.54
$14.79
Site Work
Site Work
$49.05
$45.82
$43.27
$38.31
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$3.49
$5.81
$5.35
$6.98
Base Bldg Architectural
Base Bldg Architectural
$6.22
$5.67
$7.07
$6.81
Base Bldg MEP
Base Bldg MEP
$4.05
$3.48
$7.67
$6.77
GC's and GR's & Fee
GC's and GR's & Fee
$7.38
$7.32
$7.48
$6.91
Contingency
Contingency
$84.33
$83.36
$87.39
$80.57
Total Cost
Total Cost
INLAND EMPIRE
INDIANAPOLIS
Medium Large
Medium Large
$11.04
$9.25
$17.47
$15.44
Site Work
Site Work
$42.98
$40.57
$37.35
$37.61
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$9.45
$10.91
$6.02
$6.78
Base Bldg Architectural
Base Bldg Architectural
$7.30
$6.10
$7.73
$8.01
Base Bldg MEP
Base Bldg MEP
$7.20
$5.99
$2.97
$2.11
GC's and GR's & Fee
GC's and GR's & Fee
$7.27
$6.79
$6.98
$6.88
Contingency
Contingency
$85.25
$79.62
$78.52
$76.83
Total Cost
Total Cost
LOS ANGELES
KANSAS CITY
Medium Large
Medium Large
$11.72
$9.84
$11.93
$11.41
Site Work
Site Work
$44.41
$41.70
$41.19
$37.34
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$10.25
$11.69
$4.72
$5.62
Base Bldg Architectural
Base Bldg Architectural
$7.81
$6.50
$6.54
$5.61
Base Bldg MEP
Base Bldg MEP
$7.42
$6.20
$5.09
$4.12
GC's and GR's & Fee
GC's and GR's & Fee
$7.61
$7.08
$6.68
$6.20
Contingency
Contingency
$89.22
$83.01
$76.15
$70.31
Total Cost
Total Cost
NOTES: 1. Medium (476,400 RSF) 2. Large (901,000 RSF) 3. All costs in USD; conversions made using 2022 rates
28 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
LOCALMARKETDATA
LOUISVILLE
MEMPHIS
Medium Large
Medium Large
$15.66
$12.76
$11.12
$10.54
Site Work
Site Work
$34.56
$33.79
$38.61
$35.21
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$4.77
$6.15
$4.68
$6.17
Base Bldg Architectural
Base Bldg Architectural
$8.92
$8.60
$5.22
$4.81
Base Bldg MEP
Base Bldg MEP
$4.78
$3.54
$6.30
$5.21
GC's and GR's & Fee
GC's and GR's & Fee
$6.58
$6.27
$6.23
$5.86
Contingency
Contingency
$75.27
$71.10
$72.15
$67.81
Total Cost
Total Cost
MIAMI
MILWAUKEE
Medium Large
Medium Large
$13.62
$13.02
$12.26
$11.72
Site Work
Site Work
$47.01
$42.62
$42.31
$38.36
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$5.38
$6.42
$4.84
$5.78
Base Bldg Architectural
Base Bldg Architectural
$7.46
$6.40
$6.71
$5.76
Base Bldg MEP
Base Bldg MEP
$5.81
$4.70
$5.23
$4.23
GC's and GR's & Fee
GC's and GR's & Fee
$7.63
$7.08
$6.87
$6.37
Contingency
Contingency
$86.91
$80.24
$78.22
$72.22
Total Cost
Total Cost
MINNEAPOLIS
NASHVILLE
Medium Large
Medium Large
$12.39
$11.84
$11.46
$10.87
Site Work
Site Work
$42.75
$38.76
$39.81
$36.30
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$4.90
$5.84
$4.82
$6.36
Base Bldg Architectural
Base Bldg Architectural
$6.78
$5.82
$5.38
$4.96
Base Bldg MEP
Base Bldg MEP
$5.28
$4.28
$6.49
$5.37
GC's and GR's & Fee
GC's and GR's & Fee
$6.94
$6.44
$6.43
$6.04
Contingency
Contingency
$79.04
$72.98
$74.38
$69.91
Total Cost
Total Cost
NOTES: 1. Medium (476,400 RSF) 2. Large (901,000 RSF) 3. All costs in USD; conversions made using 2022 rates
29
CUSHMAN & WAKEFIELD
LOCALMARKETDATA
NEW JERSEY
OAKLAND
Medium Large
Medium Large
$17.49
$13.97
$13.45
$11.42
Site Work
Site Work
$37.37
$34.02
$57.21
$54.12
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$6.02
$6.14
$5.09
$6.33
Base Bldg Architectural
Base Bldg Architectural
$7.73
$7.25
$6.90
$5.49
Base Bldg MEP
Base Bldg MEP
$2.97
$1.90
$8.95
$7.42
GC's and GR's & Fee
GC's and GR's & Fee
$6.99
$6.22
$8.48
$7.85
Contingency
Contingency
$78.57
$69.49
$100.08
$92.64
Total Cost
Total Cost
ORANGE COUNTY
PENN CORRIDOR
Medium Large
Medium Large
$11.38
$9.55
$17.22
$13.67
Site Work
Site Work
$43.46
$40.81
$36.79
$33.28
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$9.65
$11.10
$5.93
$6.00
Base Bldg Architectural
Base Bldg Architectural
$7.39
$6.18
$7.61
$7.09
Base Bldg MEP
Base Bldg MEP
$7.27
$6.06
$2.93
$1.86
GC's and GR's & Fee
GC's and GR's & Fee
$7.38
$6.87
$6.88
$6.09
Contingency
Contingency
$86.54
$80.57
$77.36
$67.99
Total Cost
Total Cost
PHILADELPHIA
PHOENIX
Medium Large
Medium Large
$17.49
$13.97
$17.09
$19.85
Site Work
Site Work
$37.37
$34.02
$40.47
$32.31
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$6.02
$6.14
$18.29
$22.19
Base Bldg Architectural
Base Bldg Architectural
$7.73
$7.25
$4.75
$4.46
Base Bldg MEP
Base Bldg MEP
$2.97
$1.90
$2.81
$2.62
GC's and GR's & Fee
GC's and GR's & Fee
$6.99
$6.22
$8.20
$7.96
Contingency
Contingency
$78.57
$69.49
$91.61
$89.40
Total Cost
Total Cost
NOTES: 1. Medium (476,400 RSF) 2. Large (901,000 RSF) 3. All costs in USD; conversions made using 2022 rates
30 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
LOCALMARKETDATA
PITTSBURGH
PORTLAND
Medium Large
Medium Large
$17.76
$14.50
$17.49
$15.14
Site Work
Site Work
$37.95
$35.32
$56.05
$52.58
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$6.12
$6.37
$6.14
$8.12
Base Bldg Architectural
Base Bldg Architectural
$7.85
$7.53
$6.89
$6.23
Base Bldg MEP
Base Bldg MEP
$3.02
$1.98
$9.01
$7.57
GC's and GR's & Fee
GC's and GR's & Fee
$7.09
$6.46
$8.92
$8.38
Contingency
Contingency
$79.79
$72.15
$104.51
$98.04
Total Cost
Total Cost
SALT LAKE CITY
SAN DIEGO
Medium Large
Medium Large
$17.09
$19.85
$12.94
$10.92
Site Work
Site Work
$40.47
$32.31
$58.66
$54.48
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$18.29
$22.19
$5.02
$6.28
Base Bldg Architectural
Base Bldg Architectural
$4.75
$4.46
$6.50
$5.23
Base Bldg MEP
Base Bldg MEP
$2.81
$2.62
$8.99
$7.42
GC's and GR's & Fee
GC's and GR's & Fee
$8.20
$7.96
$8.53
$7.81
Contingency
Contingency
$91.61
$89.40
$100.65
$92.14
Total Cost
Total Cost
SEATTLE
ST. LOUIS
Medium Large
Medium Large
$13.20
$11.17
$12.06
$11.53
Site Work
Site Work
$57.93
$54.30
$41.63
$37.75
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$5.05
$6.30
$4.77
$5.68
Base Bldg Architectural
Base Bldg Architectural
$6.70
$5.36
$6.61
$5.67
Base Bldg MEP
Base Bldg MEP
$8.97
$7.42
$5.15
$4.17
GC's and GR's & Fee
GC's and GR's & Fee
$8.51
$7.83
$6.76
$6.27
Contingency
Contingency
$100.36
$92.39
$76.98
$71.07
Total Cost
Total Cost
NOTES: 1. Medium (476,400 RSF) 2. Large (901,000 RSF) 3. All costs in USD; conversions made using 2022 rates
31
CUSHMAN & WAKEFIELD
LOCALMARKETDATA
CALGARY
MONTREAL
Medium Large
Medium Large
$16.79
$18.88
$14.24
$13.35
Site Work
Site Work
$47.80
$43.13
$41.95
$39.09
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$6.08
$6.66
$8.24
$9.28
Base Bldg Architectural
Base Bldg Architectural
$15.19
$15.19
$7.97
$8.34
Base Bldg MEP
Base Bldg MEP
$6.18
$5.39
$16.45
$15.10
GC's and GR's & Fee
GC's and GR's & Fee
$8.85
$8.58
$7.85
$7.50
Contingency
Contingency
$100.88
$97.84
$96.69
$92.67
Total Cost
Total Cost
TORONTO
VANCOUVER
Medium Large
Medium Large
$15.72
$14.54
$14.21
$12.92
Site Work
Site Work
$42.20
$37.20
$41.18
$40.01
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$5.31
$6.02
$8.20
$9.24
Base Bldg Architectural
Base Bldg Architectural
$6.31
$5.54
$7.97
$8.34
Base Bldg MEP
Base Bldg MEP
$3.72
$2.94
$13.54
$13.13
GC's and GR's & Fee
GC's and GR's & Fee
$7.15
$6.49
$7.47
$7.35
Contingency
Contingency
$80.41
$72.74
$92.58
$90.99
Total Cost
Total Cost
NOTES: 1. Medium (476,400 RSF) 2. Large (901,000 RSF) 3. All costs in USD; conversions made using 2022 rates
32 NORTH AMERICA INDUSTRIAL CONSTRUCTION COST GUIDE 2023
LOCALMARKETDATA
GUADALAJARA
MEXICO CITY
Medium Large
Medium Large
$7.48
$7.48
$7.48
$7.48
Site Work
Site Work
$27.85
$27.85
$27.85
$27.85
Base Bldg Structural & Enclosure
Base Bldg Structural & Enclosure
$7.30
$6.97
$7.30
$6.97
Base Bldg Architectural
Base Bldg Architectural
$11.76
$11.76
$11.76
$11.76
Base Bldg MEP
Base Bldg MEP
$14.15
$14.15
$14.15
$14.15
GC's and GR's & Fee
GC's and GR's & Fee
$5.52
$5.48
$5.52
$5.48
Contingency
Contingency
$74.06
$73.69
$74.06
$73.69
Total Cost
Total Cost
MONTERREY
Medium Large
$7.78
$13.55
Site Work
$28.96
$35.86
Base Bldg Structural & Enclosure
$7.59
$6.52
Base Bldg Architectural
$12.23
$9.13
Base Bldg MEP
$14.71
$3.75
GC's and GR's & Fee
$5.74
$6.65
Contingency
$77.02
$75.46
Total Cost
NOTES: 1. Medium (476,400 RSF) 2. Large (901,000 RSF) 3. All costs in USD; conversions made using 2022 rates
33
CUSHMAN & WAKEFIELD
CONTACTS
AUTHORS
BRIAN UNGLES Project & Development Services Americas Leader brian.ungles@cushwake.com DAVID SMITH Head of Occupier Insights Global Research david.smith4@cushwake.com
SANDY ROMERO Research Manager Global Research sandy.romero@cushwake.com
REGIONAL PDS LEADS
BRIAN JAFFE Western Region, Mexico + Latin America Lead Project & Development Services brian.jaffe@cushwake.com
TOM FIORETTI Central Region + Canada Lead Project & Development Services tom.fioretti@cushwake.com
RICHARD JANTZ Tri-State Region Lead Project & Development Services richard.jantz@cushwake.com
ADRIAN CONFORTI Northeast Region Lead
Project & Development Services adrian.conforti@cushwake.com
Nic Wilkinson nic.wilkinson@cushwake.com EMEA
Tom Gibson Head of PDS, Asia Pacific tom.gibson@cushwake.com ASIA PACIFIC
Andrew Carmichael Client Services, Asia Pacific andrew.carmichael@cushwake.com
About Cushman & Wakefield
Cushman & Wakefield (NYSE: CWK) is a leading global real estate services firm that delivers exceptional value for real estate occupiers and owners. Cushman & Wakefield is among the largest real estate services firms with approximately 50,000 employees in over 400 offices and 60 countries. In 2021, the firm had revenue of $9.4 billion across core services of property, facilities and project management, leasing, capital markets, valuation and other services.
To learn more, visit www.cushmanwakefield.com or follow @CushWake on Twitter.
Made with FlippingBook - Online Brochure Maker