CLIENT X
5 covered parking bays: Amount due per annum at renewal commencement: ZAR 8,814.36 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 5 covered parking bays: Amount due per annum at renewal commencement: ZAR 8,814.36 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 5 covered parking bays: Amount due per annum at renewal commencement: ZAR 8,814.36 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 5 covered parking bays: Amount due per annum at renewal commencement: ZAR 8,814.36 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 5 covered parking bays: Amount due per annum at renewal commencement: ZAR 8,814.36 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 1 uncovered parking bays: Amount due per annum at renewal commencement: ZAR 3,779.6 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 1 uncovered parking bays: Amount due per annum at renewal commencement: ZAR 3,779.6 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 1 uncovered parking bays: Amount due per annum at renewal commencement: ZAR 3,779.6 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 1 uncovered parking bays: Amount due per annum at renewal commencement: ZAR 3,779.6 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 1 uncovered parking bays: Amount due per annum at renewal commencement: ZAR 3,779.6 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 6.2 Amount due per annum at renewal commencement: ZAR 1,468,476.12 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, 4, Cl 6.1, 8 Amount due per annum at renewal commencement: ZAR 1,468,476.12 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, 4, Cl 6.1, 8 Amount due per annum at renewal commencement: ZAR 1,468,476.12 To be paid monthly in advance or before the 5th day of the each calendar month VAT payable Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, 4, Cl 6.1, 8
On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month On or before the 5th day of the each calendar month
ZAR
142,735.88 1,712,830.55
Yes
01 August 2021
Base Rent
Advanced
Monthly
31 July 2022
ZAR
Yes
01 August 2022
154,154.75 1,849,856.99
31 July 2023
Base Rent
Advanced
Monthly
ZAR
166,487.13 1,997,845.55
Yes
01 August 2023
31 July 2024
Base Rent
Advanced
Monthly
01 August 2019
ZAR
3,672.65
44,071.80
Yes
31 July 2020
Parking
Advanced
Monthly
01 August 2020
ZAR
3,966.46
47,597.54
Yes
31 July 2021
Parking
Advanced
Monthly
01 August 2021
ZAR
4,283.78
51,405.35
Yes
Parking
Advanced
Monthly
31 July 2022
01 August 2022
ZAR
4,626.48
55,517.78
Yes
31 July 2023
Parking
Advanced
Monthly
01 August 2023
ZAR
4,996.60
59,959.20
Yes
Parking
Advanced
Monthly
31 July 2024
3,779.16
01 August 2019
ZAR
314.93
Yes
31 July 2020
Parking
Advanced
Monthly
4,081.49
01 August 2020
ZAR
340.12
Yes
Parking
Advanced
Monthly
31 July 2021
4,408.01
01 August 2021
ZAR
367.33
Yes
31 July 2022
Parking
Advanced
Monthly
01 August 2022
ZAR
4,760.65
396.72
Yes
31 July 2023
Parking
Advanced
Monthly
ZAR
428.46
5,141.51
01 August 2023
Yes
31 July 2024
Parking
Advanced
Monthly
if another row is needed please insert above
Any other relevant expense information
Free Rent/Tenant Improvement Allowance
Free Rent Amount
Tenant Improvement Amount
Free Rent Months
Comments & Doc Name, Section, Page
Free Rent Days
Type
Currency
Lease Escalations (Indexation, Fixed Percentage and Fixed Amount Increases)
Base Index (If Indexation) (See Comment for Format)
Fixed Percentage Applied (If Applicable)
Rent Review Type (Fixed Amount,OpenMarketReview, CPI/Indexation)
Rent Review Effective Date (dd-mmmm-yyyy eg - 13-March-2015)
Frequency
Specific Index Name
Comments & Doc Name, Section, Page
Cap
Floor
Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 8
Annually
8%
Fixed Amount
01 August 2020
Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 8
Annually
8%
Fixed Amount
01 August 2021
Annually
8% Rent to be escalated by 8% on 01 Aug each year Renewal Lease, Pg 3, Cl 8