CordenPharma Proposal
OME
OPTIONS SUMMARY
FLATIRON PARK
Project Schedule Executive Schedule
5710 Flatiron Parkway 20-Jul-22 18-25K sqft *Assumes LOI Execution in July 2022, Lease Execution in August 2022
2022
2023
scope by
J J A S O N D J F M A M J J A S O N D
LOI execution Lease execution
Tenant Tenant
1
1 1
Test-fit, Concept Design & Concept Budget Tenant Approval of Design and Budget
BMR
Tenant
Permit Drawings, Permitting Preconstruction, Procurement
BMR BMR BMR
1 2 3 4 5 6
1 2 3 4 5 6 7 8 9
Construction Occupancy
1 2 3 4 5 6 7
1
*Above project schedule provided to a recent tenant. Estimated October 2023 occupancy based on a signed lease by August 2022.