APAC Data Centre H2 2023 Update

TYO JAPAN

H2 23

RECENT PROPERTY SALES SITE / PROPERTY SIZE

SALE DATE

SALE PRICE (US$)

BUYER

SELLER

Gotenyama SH Bldg

20,000 m 2

Oct 2023

$469M

TIS Inc

Sekisui House REIT

Hino Motors Factory Site 28 acres

Sep 2023

$344M

Mitsui Fudosan

Hino Motors

CONTACTS Click on each name to email them

CONSTRUCTION UPDATES*

OPERATOR

DATA CENTRE

LOCATION

BUILDING SIZE POWER (TOTAL CAPACITY†) STAGE - EST. RFSˆ

TODD OLSON Executive Sponsor,

TOK1 TOK2

Inzai Ome

164,270m 2 110,000m 2

27.5MW (288MW) 60MW (108MW)

U/C U/C – 2024

APAC DCAT & Managing Director, Japan & Korea todd.olson@ap.cushwake.com MARI KUMAGAI Director, Head of Research & Consulting, Japan mari.kumagai@cushwake.com KOSUKE OGI Executive Director, Capital Markets, Japan Kosuke.Ogi@ap.cushwake.com TIMOTHY GREGERSEN Senior Manager, Investment Sales, Japan timothy.gregersen@ap.cushwake.com

12MW (24)

U/C – 2024

CC3

Chuo City

32,000m 2

Inzai 4

Inzai

18,000m 2

23.1MW (36.3MW)

U/C

TY07

Chuo City

6,800m 2

1.2MW (5MW)

U/C – 2025

TY11 TY15

Koto City Minato City

24,847m 2 110,000m 2

2.6MW 3.6MW (7.5MW)

U/C U/C – 2024

19.5MW (39MW)

U/C - 2024

Fuchu Campus

Fuchu

40,000m 2

Tokyo NRT11-13

Inzai

84,000m 2

12MW (84MW)

U/C – 2024

Kanagawa Data Center

Sagamihara City

30,984m 2

12MW

U/C – 2024

TY1

Saitama

58,860m 2

48MW (96MW)

U/C – 2024

GOTEMBA Data Centre ASAMA Data Centre Campus

Kawasaki / Kanagawa Kashiwa

17,506m 2 19,561m 2

18MW 6MW (54MW)

U/C U/C

6MW (36MW)

U/C – 2024

TKY01

Inzai

44,032m 2

Inzai Campus

Inzai

60,000m 2

15MW (60MW)

U/C – 2024

* Excludes Captive & ICT construction updates. †Total IT Load ˆ RFS: Ready for Service