APAC Data Centre H2 2023 Update

HKG GREATER CHINA

H2 23

CONSTRUCTION & PLANNED UPDATES*

OPERATOR

DATA CENTRE LOCATION

BUILDING SIZE POWER (TOTAL CAPACITY†) STAGE - EST. RFSˆ

HKG2

Sha Tin

11,400m 2

4MW

U/C – 2024

10MW 30MW

U/C – 2025 Planned – 2025

Fo Tan DC / STTL 613

CONTACTS Click on each name to email them

Sha Tin

73,300m 2

JOHN SIU Managing Director, Hong Kong john.siu@cushwake.com ROSANNA TANG Executive Director, Head of Research, Hong Kong rosanna.tang@cushwake.com

40MW

Planned - 2025

HK1

Kwai Chung

27,300m 2

HK 2 HK 3 HK 4

18MW 21MW 22MW

Kwai Chung Tsuen Wan Kwai Chung

U/C - 2024 Planned – 2026 Planned – 2028 U/C – 2025 Planned – 2025 Planned – 2026

21,200m 2 22,100m 2 25,800m 2

4MW 4MW Phase 2: 8MW

Tower 3

Fanling

16,630m 2

ANTHONY WONG Research Manager, Hong Kong anthony.wong@cushwake.com

25MW

U/C – 2025

FSSTL 268

Fanling

20,100m 2

130MW

U/C – 2024

MEGA IDC

Tseung Kwan O 117,989m 2

* Excludes Captive & ICT construction updates. †Total IT Load ˆ RFS: Ready for Service