APAC Data Centre H2 2023 Update
HKG GREATER CHINA
H2 23
CONSTRUCTION & PLANNED UPDATES*
OPERATOR
DATA CENTRE LOCATION
BUILDING SIZE POWER (TOTAL CAPACITY†) STAGE - EST. RFSˆ
HKG2
Sha Tin
11,400m 2
4MW
U/C – 2024
10MW 30MW
U/C – 2025 Planned – 2025
Fo Tan DC / STTL 613
CONTACTS Click on each name to email them
Sha Tin
73,300m 2
JOHN SIU Managing Director, Hong Kong john.siu@cushwake.com ROSANNA TANG Executive Director, Head of Research, Hong Kong rosanna.tang@cushwake.com
40MW
Planned - 2025
HK1
Kwai Chung
27,300m 2
HK 2 HK 3 HK 4
18MW 21MW 22MW
Kwai Chung Tsuen Wan Kwai Chung
U/C - 2024 Planned – 2026 Planned – 2028 U/C – 2025 Planned – 2025 Planned – 2026
21,200m 2 22,100m 2 25,800m 2
4MW 4MW Phase 2: 8MW
Tower 3
Fanling
16,630m 2
ANTHONY WONG Research Manager, Hong Kong anthony.wong@cushwake.com
25MW
U/C – 2025
FSSTL 268
Fanling
20,100m 2
130MW
U/C – 2024
MEGA IDC
Tseung Kwan O 117,989m 2
* Excludes Captive & ICT construction updates. †Total IT Load ˆ RFS: Ready for Service
20
Made with FlippingBook Digital Publishing Software