Asia Pacific Data Centre Update

HCM VIETNAM

H2 22

RECENT SITE SALES SITE

SIZE

SALE DATE

SALE PRICE (US$) BUYER

SELLER

Saigon Hi-Tech Park Parcel

6,056m 2

June 2022

(Confidential)

GAW Capital

Saigon Hi-Tech park

CONSTRUCTION & PLANNED UPDATES*

CONTACTS Click on each name to email them

OPERATOR

DATA CENTRE

LOCATION

SIZE

POWER STAGE - EST. DELIVERY

EPZ Tan Thuan Data Center Fornix Data Center (HCMC)

District 7 District 9

Phase 2 data hall: 560m 2 Total building size: 20,000m 2 Phase 2 data hall: 6,000m 2

0.8MW 5MW 7.5MW

Planned U/C - 2023 Planned

TRANG BUI General Manager, Vietnam bui.trang@cushwake.com

Total building size: 5,000m 2 Phase 2 data hall: 1,500m 2

2.4MW 3.6MW

U/C Planned

JOHN LE Senior Manager, Leasing Agency – Industrial, Thailand John.Le@cushwake.com

Tan Thuan Data Center

District 7

0.4MW Planned

IDC Tan Thuan

District 7

Phase 2 data hall: 400m 2

* Excludes Captive & ICT construction updates.