Asia Pacific Data Centre Update

H2 22 JKT INDONESIA

RECENT SITE SALES SITE

SIZE

SALE DATE

SALE PRICE (US$) BUYER

SELLER

Cikarang

~ 10 acres

~ February 2022

(Confidential)

EdgeConneX

MLPT

JAK2

(Unknown)

August 2022

(Confidential)

AticaDC

SpaceDC

Eastern Jakarta

(Unknown)

February 2022

(Confidential)

EdgeConneX

MLPT

CONTACTS Click on each name to email them

Squared Capital

Indosat Ooredoo Jakarta

10,884m 2

June 2022

$117,200,000

Indosat Ooredoo

Squared Capital

Indosat Ooredoo Jatiluhur

8,421m 2

June 2022

$90,600,000

Indosat Ooredoo

ARIEF RAHARDJO Director, Strategic Consulting Indonesia Arief.rahardjo@ap.cushwake.com WIRA AGUS Director, Industrial & Land Sales, Indonesia wira.agus@ap.cushwake.com

Squared Capital

Lintasarta Technopark

6,229m 2

June 2022

$67,100,000

Indosat Ooredoo

Squared Capital

Lintasarta TBS

1,678m 2

June 2022

$18,100,000

Indosat Ooredoo

CONSTRUCTION UPDATES*

OPERATOR

DATA CENTRE

LOCATION BUILDING SIZE POWER

STAGE – EST. RFS

Greenland Intl. Industrial Center (GIIC) Bekasi

35,100m²

38.4MW

U/C

CGK2 Technopark BSD

Phase 2: 2MW

U/C

Banten

6,001m²

H2-02 JK5

Karawang Cikarang

12,000m² 16,666m²

12MW Phase 2: 7.5MW

U/C – Q4 2022 U/C

Edge1 Edge2

Jakarta Jakarta

7,500m² 17,150m²

Phase 2: 1MW 23MW

U/C U/C – Q4 2023

Phase 1: 12MW Phase 2: 12MW

U/C – Oct 2023 Planned

ID02

Kuningan

35,000m²

GIIC KIIC

Bekasi Karawang

20,631.42 m² 20,631.58m²

Phase 1: 5MW Phase 1: 5 MW Phase 2: 14.6 MW

U/C U/C U/C

Jakarta 2 Data Center

Kuningan

15,400m²

Next phase: 1.8MW U/C

JC2

Jawa Barat

22,800m²

22MW

U/C – Q4 2022

Pure Data Centres

Bekasi

20,000m²

20MW

U/C

GIIC

Bekasi

20,000m²

Phase 1: 16MW

U/C – Q1 2023

* Excludes Captive & ICT construction updates.