Asia Pacific Data Centre Update
H2 22 SEL
RECENT SITE & PROPERTY SALES SITE / PROPERTY SIZE
SOUTH KOREA
SALE DATE
SALE PRICE (US$)
BUYER
SELLER
Fmr Kyung Dong Navien R&D Building
1 acre
April 2022
$46,526,271
Gasan
Daelim
Seil Steel Industrial Building
2 acres
January 2022
$61,882,608
KORAMCO
Seil Steel Co Ltd
CONTACTS Click on each name to email them
IMM Investment Group
23,146 m²
Dreammark1
April 2022
(Confidential)
Gaw Capital
JOHN PRITCHARD Head of Tenant Advisory Group, Korea john.pritchard@cushwake.com JINWOO JUNG Head of Research, Korea jinwoo.jung@cushwake.com
CONSTRUCTION UPDATES*
OPERATOR
DATA CENTRE
LOCATION BUILDING SIZE POWER
STAGE - EST. RFS
Pyeongchon Data Centre Youngdeungpo Data Centre
Anyang Youngdeungpo
25,000m 2 25,000m 2
26MW YDC Phase 1: 13MW Phase 2:13MW
U/C – 2024 YDS Phase 1: U/C – 2025
Phase 1: 10.6MW
U/C – 2023
Digital Seoul 2 (ICN11)
Gimpo
90,115m 2
Gangnam IDC
Gangnam
40,000m 2
Phase 1: 10MW
U/C - 2024
SL2x
Hyangdong
13,000m 2
SL2x Phase 1: 12MW U/C – 2024
Gasan Iwill Data Centre
Geumcheon
36,518m 2
Phase 1: 13MW
U/C – 2025
Pacific Sunny Data Centre Jukjeon
99,070m 2
Phase 1: 16MW
U/C – Q2 2024
40,450m 2 7,100m 2
Pyeongchon 2
Anyang
Phase 1: 12MW
U/C – Q3 2023
Bundang Center
Bundang
11,570m²
Phase 2: 6MW
U/C
* Excludes Captive & ICT construction updates.