APAC Data Centre Update: H1 2024

JKT INDONESIA

H1 24

SIGNIFICANT CONSTRUCTION & PLANNED UPDATES*

COMPANY

DATA CENTRE

LOCATION

POWER (TOTAL CAPACITY†)

STAGE - EST. RFSˆ

CKG1 CGK3A

Jakarta Jakarta

Phase 1: 3MW(8MW) Phase 1: 5MW (15MW)

U/C U/C

BDx

CONTACTS Click on each name to email them

E1 Data Center Campus

East Kuningan

8MW (18MW)

U/C - 2024

H1-JK5 H1-JK6 E1 H2-01 H2-02

Bekasi Bekasi Jakarta

Final phase: 3MW (15MW) Phase 1: 9MW (36MW) Phase 2: 4MW (19MW) Phase 2: 5MW (15MW) Final phase: 10MW (12MW)

ARIEF RAHARDJO Director, Strategic Consulting Indonesia Arief.rahardjo@ap.cushwake.com WIRA AGUS Director, Industrial & Land Sales, Indonesia wira.agus@ap.cushwake.com

U/C – 2024

Karawang Karawang

Edge2

Jakarta

18.75 (23MW)

Planned

Bekasi

Bekasi

Phase 1: 10MW (57.6MW)

U/C – 2025

Equinix

JK1

Jakarta

Phase 1: 3.5MW (7MW)

U/C – 2025

K2 Data Centres

JKT1

Bekasi

Phase 1: 8.4MW (58.8MW)

U/C – 2024

ID01 ID02

Bekasi Bekasi

20MW (30MW) 2.4MW (24MW)

U/C Planned

JKT2 Jakarta 3

Jakarta Jakarta

12MW (12MW) 15.2MW (45MW)

Planned U/C

NTT Data

* Excludes Captive & ICT construction updates. †Total IT Load ˆ RFS: Ready for Service

CUSHMAN & WAKEFIELD | ASIA PACIFIC DATA CENTRE MARKET OVERVIEW