APAC Data Centre Update: H1 2024

HKG GREATER CHINA

H1 24

SIGNIFICANT CONSTRUCTION & PLANNED UPDATES*

COMPANY

DATA CENTRE

LOCATION

POWER (TOTAL CAPACITY†)

STAGE - EST. RFSˆ

U/C – 2025 U/C – 2026

HKG1 HKG2

Tsuen Wan Sha Tin

4MW (20MW) 9MW (15MW)

Airtrunk

CONTACTS Click on each name to email them

Chinachem Group

Tung Chung Data Centre

Tung Chung

30MW (30MW)

Planned – 2027

JOHN SIU Managing Director, Hong Kong john.siu@cushwake.com

10MW (27MW) 30MW (84MW)

U/C – 2025 Planned – 2025

China Mobile

STTL 613

Sha Tin

14MW (14MW) 70MW (70MW)

U/C – 2025 U/C – 2028

China Telecom

Tseung Kwan O Data Centre Tseung Kwan O

ROSANNA TANG Head of Research, Hong Kong rosanna.tang@cushwake.com THOMAS CHAN Associate Director, Research, Hong Kong thomas.chan@cushwake.com

HK1

Kwai Chung

Phase 1: 21MW

Planned – Q3 2027

HK 2 HK 3 HK 4

Kwai Chung Tsuen Wan Kwai Chung

18MW (18MW) 21MW (21MW) 22MW (22MW)

U/C - 2024 Planned – 2026 Planned – 2028

GDS

Goodman

Texaco Centre

Tsuen Wan

32MW (32MW)

Planned - 2027

Tower 3.1

Fanling

12MW (24MW) 12MW (24MW) 8MW (8MW)

U/C – 2025 Planned – 2025 Planned – 2026

Tower 3.2

Fanling

Mapletree

Mapletree TM

Fanling

25MW (25MW)

U/C – 2025

MEGA IDC

Tseung Kwan O

130MW (130MW)

U/C – 2024

* Excludes Captive & ICT construction updates. †Total IT Load ˆ RFS: Ready for Service

CUSHMAN & WAKEFIELD | ASIA PACIFIC DATA CENTRE MARKET OVERVIEW

Made with FlippingBook - Online magazine maker