TRUNG TÂM DỮ LIỆU
Bảng chi phí xây dựng giả định Phát triển dự án đa tầng (quy mô 1 0 mẫu (~4 hectares) + công suất 50MW) (1/2)
Giá đất
Chi phí xây dựng
Thị trường
Thấp USD/m 2
Trung bình USD/m 2
Cao USD/m 2
Thấp USD/MW
Trung bình USD/MW
Cao USD/MW
Melbourne
$243
$554
$865
$7,242,413
$9,173,723
$11,105,033
Úc
Perth
$162
$262
$362
$7,242,413
$9,173,723
$11,105,033
Sydney
$470
$960
$1,449
$7,242,413
$9,173,723
$11,105,033
Bắc Kinh
$384
$4,721
$9,057
$5,397,600
$6,836,960
$8,276,320
Thượng Hải
$361
$3,113
$5,866
$5,397,600
$6,836,960
$8,276,320
Trung Quốc Đại Lục
Thẩm Quyến
$224
$2,761
$5,298
$5,397,600
$6,836,960
$8,276,320
Thiên Tân
$242
$1,269
$2,296
$5,397,600
$6,836,960
$8,276,320
Tung Chung
$1,607
$1,874
$2,142
$7,261,800
$9,198,280
$11,134,760
Truân Môn& Nguyên Lãng
$2,678
$2,945
$3,213
$7,261,800
$9,198,280
$11,134,760
Phấn Lĩnh, Sheung Shui, Đại Bộ
$2,678
$3,213
$3,749
$7,261,800
$9,198,280
$11,134,760
Hông Kông
Quỳ Dũng, Thuyên Loan, Thanh Y, Sa Điền
$3,213
$4,284
$5,355
$7,261,800
$9,198,280
$11,134,760
Đông Cửu Long& Hong Kong Est.
$4,820
$6,694
$8,568
$7,261,800
$9,198,280
$11,134,760
Tseung Kwan O Industrial Estate
$1,392
$1,499
$1,607
$7,261,800
$9,198,280
$11,134,760
Đài Bắc
$1,619
$2,052
$2,484
$4,857,840
$6,153,264
$7,448,688
Đài Loan
Kaohsiung
$938
$1,251
$1,439
$4,857,840
$6,153,264
$7,448,688
Đài Trung
$1,924
$2,366
$2,808
$4,857,840
$6,153,264
$7,448,688
Bangalore
$478
$1,355
$2,233
$5,358,600
$6,787,560
$8,216,520
Chennai
$160
$638
$1,116
$5,358,600
$6,787,560
$8,216,520
Ấn Độ
Delhi
$637
$1,435
$2,233
$5,358,600
$6,787,560
$8,216,520
Hyderabad
$176
$1,045
$1,914
$5,358,600
$6,787,560
$8,216,520
Mumbai
$192
$1,691
$3,189
$5,358,600
$6,787,560
$8,216,520