Life Sciences U.S. Fit-Out Cost Guide 2025
Cost Segmentation Fit out costs are grouped into nine segments: Misc. Architectural Trades; Arch. Millwork; Doors, Frames, Hardware; Drywall, Acoustic, Carpentry; General Finishes; Special Construction (Clean Rooms/Cold Rooms); Mechanical, Plumbing, Fire Protection; Electrical; General Conditions & Fee; and Contingency. An average of 46% of total expenses were attributed to Mechanical, Plumbing, and Fire Protection across all markets and asset types. General Conditions & Fee followed at 14%, with Special Construction (Clean Rooms/Cold Rooms) at 11%. Most cost allocations remained stable from last year However, Mechanical, Plumbing, Fire Protection saw a notable YOY increase of $23 psf (6.2%).
Across both market and subtype levels, the greatest proportion of cost is generally allocated to Mechanical, Pluming, Fire Protection, with the exception of warehouse costs. 28% of warehouse costs are distributed to Special Construction (Clean Rooms/Cold Rooms), while another 19% is allocated to Mechanical, Plumbing, and Fire Protection. Gene/Cell Therapy also sees a significant portion of costs apportioned to Special Construction (Clean Rooms/Cold Rooms) at 22%.
TENANT IMPROVEMENT COSTS BY MARKET (LEFT) AND FACILITY TYPE (RIGHT)
Misc. Architectural Trades Doors, Frames, Hardware
Arch. Millwork
Drywall, Acoustic, Carpentry
General Finishes
Special Construction (Clean Rooms/Cold Rooms)
Mechanical, Plumbing, Fire Protection
Electrical
General Conditions and Fee
Contingency
San Francisco, CA
BSL3
San Francisco, CA
Gene/Cell Therapy
Philadelphia, PA
cGMP Bulk Manufacturing
Vivarium
Boston, MA
Chemistry
Seattle, WA
Analytical (CLIA)
BSL1 & BSL2
San Diego, CA
Office
Raleigh-Durham, NC
Warehouse
0% 20% 40% 60% 80% 100%
0% 20% 40% 60% 80% 100%
Source: Cushman & Wakefield Project & Development Services
14