Fit Out Cost Guide 2025 | Legal Sector

Legal Cost Data - SecondaryMarkets

MIAMI

BASE

Low Range

High Range

Misc. Architectural Trades

$3

$3

Arch. Millwork

$6

$6

Doors, Frames, Hdwr

$19

$19

Drywall, Acoustic, Carpentry

$23

$23

General Finishes

$8

$8

Mechanical, Plumbing, Fire Protection

$40

$40

Electrical

$42

$42

General Requirements, General Conditions & Fee

$18

$18

Contingency

$16

$16

Cost Guide Total

$176

$176

Soft Costs

$21

$33

IT

$10

$15

A/V

$25

$40

Furniture

$39

$62

Miscellaneous

$1

$2

Legal Build Out Total

$97

$152

Total

$274

$328

MINNEAPOLIS

BASE

Low Range

High Range

Misc. Architectural Trades

$4

$4

Arch. Millwork

$8

$8

Doors, Frames, Hdwr

$21

$21

Drywall, Acoustic, Carpentry

$21

$21

General Finishes

$13

$13

Mechanical, Plumbing, Fire Protection

$24

$24

Electrical

$20

$20

General Requirements, General Conditions & Fee

$14

$14

Contingency

$12

$12

Cost Guide Total

$137

$137

Soft Costs

$16

$26

IT

$8

$12

A/V

$20

$31

Furniture

$31

$48

Miscellaneous

$1

$2

Legal Build Out Total

$75

$118

Total

$212

$254