Data Center Development Cost Guide 2025
DATA CENTER DEVELOPMENT COST GUIDE 2025
CONSTRUCTION COSTS BY MARKET
SELECT MARKETS: DATA CENTER CONSTRUCTION COST PER MW
$16
$15.0
$15
$14.3
$14.2
$14.1
$13.9
$13.7
$14
$13.4
$13.4
$13.2
$13.0
$12.9
$13
$12.6
$12.4
$12.4
$12.3
$12.2
$12.1
$12.1
$11.9
$12.5
$12
$11
$11.1
$11.1
$11.0
$10.8
$10.8
$10.6
$10
$10.4
$10.4
$10.1
$10.0
Millions USD/MW
$9.8
$9.7
$9.7
$9.7
CONSTRUCTION COST COMPONENTS
$9.5
$9
$9.4
$9.4
$9.3
$8
UNITED STATES: MATERIAL COST CHANGES
Reno
Dallas
Austin
Omaha
Material Cost Changes Index (Q3 2021 = 100)
Impact of Lead Time on Material Cost Index
Atlanta
Newark
Virginia
Phoenix
Chicago
Portland
Cheyenne
Las Vegas
Columbus
Des Moines
Wenatchee
Kansas City
San Antonio
Salt Lake City
San Francisco
Low (U.S. $M/MW)
Mid (U.S. $M/MW)
High (U.S. $M/MW)
160
115
110
150
Source: Cushman & Wakefield Research, Turton Bond
105
140
100
130
30+ Weeks → +6%
30+ Weeks → +5%
46+ Weeks → +14%
28+ Weeks → +15%
28+ Weeks → +9%
28+ Weeks → +7%
Across 19 markets, the cost to develop one megawatt (MW) of critical load varied from $15 million in Reno on the high end to $9.3 million in San Antonio on the low end, with an average of $11.7 million. Texas emerged as a cost-effective option compared to other data center markets, as Dallas, Austin and San Antonio recorded lower costs per MW than any of the other 16 markets analyzed. This cost advantage can be attributed to Texas’ business-friendly regulatory environment, attractive incentive packages, reasonable site acquisition costs and access to affordable labor. The construction cost analysis in the above chart excluded typical owner-furnished contractor installed (OFCI) equipment purchases, end user/ tenant costs, operational costs, land acquisition,
design/soft costs and owner-held contingencies. Therefore, the affordability of land in markets like Des Moines and Reno was not factored in. These two markets, however, faced inflated labor expenses, largely due to the lack of skilled local labor, requiring developers to offer incentives and cover travel expenses to bring in workers. Virginia, home to the largest data center market, ranked as the seventh least expensive among the 19 markets. Its data center-friendly environment and long-standing industry presence have fostered economies of agglomeration, where clusters of data center activity drive cost efficiencies for developers, owners, operators and tenants, ultimately creating a competitive market.
95
120
90
110
UPS
100
Chillers
Q3 2021
Q2 2022
Q1 2023
Q4 2023
Q3 2024
CX Boards
Generators
Switchgear
Transformers
Switchgear CX Boards
Generators
Transformers
Order Date Cost (Q3 2023)
Cost After Lead Time
UPS
Chillers
Note: Indexed values – Q3 2023 = 100 Source: Cushman & Wakefield Research, Turton Bond
Source: Cushman & Wakefield Research, Turton Bond
Since the pandemic, strained supply chains have made materials acquisition difficult and more expensive. Since the third quarter of 2021, switchgear prices have risen by 50%. This cost surge extends to a variety of materials required for data center construction, including generators
(+45%), transformers (+44%), CX boards (+31%), UPS (+48%) and chillers (+40%). These price escalation0s, combined with elevated labor expenses, have directly driven up data center development costs.
8
9
Cushman & Wakefield
Made with FlippingBook - Online magazine maker