CordenPharma Proposal
HO
TIMELINE
TIMELINE This illustrates a realistic timeline for identifying and building new lab space in Boulder. Our team will work quicker than anyone to expedite the due diligence & lease execution process, but the construction process creates the longest delay. Permitting in the city of Boulder along with supply chain issues for generators, HVAC rooftop units, switch gear, and other lab equipment continuously extend construction timelines. Our detailed understanding of the progress landlords have made to proactively expedite these timelines will be key to getting CordenPharma into space as quickly as possible.
STRATEGIC ASSESSMENT & MARKET TOURS
TERM SHEET NEGOTIATION & BUILDING DUE DILIGENCE
LEASE NEGOTIATIONS
2 MONTHS
2 MONTHS
2 MONTHS
DUE DILIGENCE & LEASE EXECUTION = 6 MONTHS
1.5 YEAR
18 CORDENPHARMA Proposal for Real Estate Services