Americas Office Fit Out Cost Guide 2023

OFFICE FIT OUT COST GUIDE 2023

LOCALMARKETDATA

BOSTON

CALGARY (LC)

2022

2023

2022

2023

$3.36

$10.84

3.93

4.63

Misc. Architectural Trades

Misc. Architectural Trades

$8.43

$9.41

7.23

8.54

Arch. Millwork

Arch. Millwork

$15.54

$16.40

14.06

16.59

Doors, Frames, Hdwr

Doors, Frames, Hdwr

$20.18

$17.82

18.65

22.00

Drywall, Acoustic, Carpentry

Drywall, Acoustic, Carpentry

$10.48

$11.02

9.58

11.30

General Finishes

General Finishes

Mechanical, Plumbing, Fire Protection

Mechanical, Plumbing, Fire Protection

$31.61

$36.34

17.55

20.71

$25.92

$26.98

22.60

26.67

Electrical

Electrical

General Requirements, General Conditions & Fee

General Requirements, General Conditions & Fee

$17.13

$14.82

15.66

18.48

$13.12

$13.07

10.93

12.89

Contingency

Contingency

$145.77

$156.70

120.18

141.81

Total

Total

CHARLOTTE

CHICAGO

2022

2023

2022

2023

$3.11

$3.06

$4.33

$5.03

Misc. Architectural Trades

Misc. Architectural Trades

$4.34

$4.90

$6.82

$9.74

Arch. Millwork

Arch. Millwork

$9.23

$12.81

$12.56

$10.83

Doors, Frames, Hdwr

Doors, Frames, Hdwr

$15.37

$17.49

$20.83

$21.11

Drywall, Acoustic, Carpentry

Drywall, Acoustic, Carpentry

$7.87

$8.81

$9.58

$9.63

General Finishes

General Finishes

Mechanical, Plumbing, Fire Protection

Mechanical, Plumbing, Fire Protection

$16.75

$20.92

$24.25

$35.82

$28.15

$29.39

$32.50

$35.29

Electrical

Electrical

General Requirements, General Conditions & Fee

General Requirements, General Conditions & Fee

$10.45

$10.69

$13.96

$13.64

$7.67

$10.31

$12.39

$13.30

Contingency

Contingency

$102.95

$118.39

$137.24

$154.39

Total

Total

NOTES: LC=Local Currency All costs are GEN 1 GEN 2 costs have a 10-15% discount