Americas Fit-Out Cost Guide 2022
LOCALMARKETDATA
CHILE
CINCINNATI
Local currency
1st Generation
1st Generation
$15.09
11,233.31
$2.48
Misc. Architectural Trades
Misc. Architectural Trades
$2.16
1,609.24
$5.50
Arch. Millwork
Arch. Millwork
$5.04
3,750.00
$11.95
Doors, Frames, Hdwr
Doors, Frames, Hdwr
$5.15
3,834.30
$13.01
Drywall, Acoustic, Carpentry
Drywall, Acoustic, Carpentry
$5.86
4,362.73
$11.33
General Finishes
General Finishes
Mechanical, Plumbing, Fire Protection
Mechanical, Plumbing, Fire Protection
$9.87
7,351.05
$18.16
$11.61
8,642.68
$18.82
Electrical
Electrical
General Requirements, General Conditions & Fee
General Requirements, General Conditions & Fee
$29.63 22,061.88
$10.05
$8.44
6,284.52
$9.13
Contingency
Contingency
$92.84 69,129.70
$100.43
Total
Total
COLOMBIA
COLUMBUS
Local currency
1st Generation
1st Generation
$11.86
40,380.37
$2.53
Misc. Architectural Trades
Misc. Architectural Trades
$3.76
12,783.02
$5.60
Arch. Millwork
Arch. Millwork
$5.46
18,599.40
$12.17
Doors, Frames, Hdwr
Doors, Frames, Hdwr
$7.10
24,153.42
$13.25
Drywall, Acoustic, Carpentry
Drywall, Acoustic, Carpentry
$11.43
38,896.89
$11.54
General Finishes
General Finishes
Mechanical, Plumbing, Fire Protection
Mechanical, Plumbing, Fire Protection
$13.24 45,074.73
$18.52
$10.04
34,172.29
$19.21
Electrical
Electrical
General Requirements, General Conditions & Fee
General Requirements, General Conditions & Fee
$10.24
$10.67 36,329.28
$9.30
Contingency
$3.52
11,996.57
Contingency
$102.35
Total
Total
$77.09 262,385.97
NOTES: 1. Generation 1 costs
2. Generation 2 costs have a 10-15% discount 3. All costs in USD unless otherwise noted
22
AMERICAS OFFICE FIT-OUT COST GUIDE 2022
Made with FlippingBook PDF to HTML5