Americas Data Center H2 2024 Update

RECENT SALES SITE / PROPERTY

ATL UNITED STATES

H2 24

SIZE

SALE DATE

SALE PRICE (US$) BUYER

SELLER

2525 Westside Pky, Alpharetta

240,226 sf

Dec-24

$40M

Lincoln Property Company DXC Technology Company

7800 Strickland St, Douglasville

129 acres

Nov-24

$64.7M

Amazon

TPA Group

2111 Powell Rd, Augusta

212 acres

Oct-24

$31.2M

QTS

Barbara W Sims

Veterans Pky, Fayetteville

204 acres

Sep-24

$39.8M

QTS

Huffman Group

2335 Echo Rd, Lithia Springs

119 acres

Sep-24

$37.1M

Amazon

Taylor & Mathis, Inc.

CONTACTS Click on each name to send an email.

Gullatt Rd, Palmetto

92 acres

Aug-24

$40.7M

T5 Data Centers

Red Rock Developments

2 Gene Allen Rd, Hampton

262 acres

Jul-24

$118M

Equinix

Powergrid Real Estate

151 Etowah Ridge Trl SE, Cartersville 29 acres

Jul-24

$0.3M

Switch

E T Properties Inc.

JOHN McWILLIAMS Head of Data Center Insights, Global Think Tank +1 (303) 312-4233 john.mcwilliams@cushwake.com

4830 Stonewall Tell Rd, College Park 65 acres

Jul-24

$318.5M

EdgeConneX

TA Realty

411 Pegasus Pky, Lagrange

268 acres

Jul-24

$50M

Thor Equities

Jindal Films Americas LLC

SIGNIFICANT CONSTRUCTION & PLANNED UPDATES

OPERATOR

DATA CENTER

SIZE (SF)

POWER (MW)

STAGE - EST. DELIVERY

ATL 4 ATL 5

387,500 968,750

40 120

U/C In Planning

DataBank

Douglasville – Phase 1 Douglasville – Remaining Phases Conyers

1,000,000 250,000 1,000,000 300,000 450,000 450,000 466,000 1,198,000 250,000 490,000 245,000 490,000 2,474,830 4,124,700 385,000

80 120 160 (est.)

U/C – Q4 2025 In Planning In Planning

DC Blox

Digital Realty

10 Forsyth

28

In Planning U/C In Planning

Tilford Yard – Phase 2 Tilford Yard – Remaining Phases

100 (est.) 41 (est.)

Edged Energy

Flexential

Douglasville – Phase 2

90,000 (est.)

13.5 43 265

U/C

Stanton Springs 2 – Phase 2 Stanton Spring 2 – Remaining Phases

U/C – 2026 In Planning U/C U/C U/C In Planning

Meta

Palmetto – Phase 1 Douglasville – Phase 1 East Point – Phase 1 Project Rita

26 40

Microsoft

57 (est) 96 (est)

Atlanta 2 – Phase 1 Atlanta 2 – Remaining Phases Suwanee DC 1 - Expansion

288 480 32

U/C In Planning - 2032 In Planning

QTS

STACK Infrastructure

Lithia Springs – Phase 1

87,890

12

U/C

KEEP - Expansion KEEP 2.0 – Phase 1

279,860 413,980

70 60

U/C In Planning – Q2 2026

Switch

Atlanta III – Phase 1 Atlanta III – Remaining Phases Atlanta IV

162,490 1,500,960 2,842,360 1,660,000

20 198 300

U/C In Planning In Planning In Planning

T5 Data Centers

Vantage Data Centers

Douglasville

96

*Excludes Captive & ICT construction updates.

†Total IT Load

ˆ RFS: Ready for Service

CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW

Made with FlippingBook Ebook Creator