Americas Data Center H2 2024 Update
RECENT SALES SITE / PROPERTY
ATL UNITED STATES
H2 24
SIZE
SALE DATE
SALE PRICE (US$) BUYER
SELLER
2525 Westside Pky, Alpharetta
240,226 sf
Dec-24
$40M
Lincoln Property Company DXC Technology Company
7800 Strickland St, Douglasville
129 acres
Nov-24
$64.7M
Amazon
TPA Group
2111 Powell Rd, Augusta
212 acres
Oct-24
$31.2M
QTS
Barbara W Sims
Veterans Pky, Fayetteville
204 acres
Sep-24
$39.8M
QTS
Huffman Group
2335 Echo Rd, Lithia Springs
119 acres
Sep-24
$37.1M
Amazon
Taylor & Mathis, Inc.
CONTACTS Click on each name to send an email.
Gullatt Rd, Palmetto
92 acres
Aug-24
$40.7M
T5 Data Centers
Red Rock Developments
2 Gene Allen Rd, Hampton
262 acres
Jul-24
$118M
Equinix
Powergrid Real Estate
151 Etowah Ridge Trl SE, Cartersville 29 acres
Jul-24
$0.3M
Switch
E T Properties Inc.
JOHN McWILLIAMS Head of Data Center Insights, Global Think Tank +1 (303) 312-4233 john.mcwilliams@cushwake.com
4830 Stonewall Tell Rd, College Park 65 acres
Jul-24
$318.5M
EdgeConneX
TA Realty
411 Pegasus Pky, Lagrange
268 acres
Jul-24
$50M
Thor Equities
Jindal Films Americas LLC
SIGNIFICANT CONSTRUCTION & PLANNED UPDATES
OPERATOR
DATA CENTER
SIZE (SF)
POWER (MW)
STAGE - EST. DELIVERY
ATL 4 ATL 5
387,500 968,750
40 120
U/C In Planning
DataBank
Douglasville – Phase 1 Douglasville – Remaining Phases Conyers
1,000,000 250,000 1,000,000 300,000 450,000 450,000 466,000 1,198,000 250,000 490,000 245,000 490,000 2,474,830 4,124,700 385,000
80 120 160 (est.)
U/C – Q4 2025 In Planning In Planning
DC Blox
Digital Realty
10 Forsyth
28
In Planning U/C In Planning
Tilford Yard – Phase 2 Tilford Yard – Remaining Phases
100 (est.) 41 (est.)
Edged Energy
Flexential
Douglasville – Phase 2
90,000 (est.)
13.5 43 265
U/C
Stanton Springs 2 – Phase 2 Stanton Spring 2 – Remaining Phases
U/C – 2026 In Planning U/C U/C U/C In Planning
Meta
Palmetto – Phase 1 Douglasville – Phase 1 East Point – Phase 1 Project Rita
26 40
Microsoft
57 (est) 96 (est)
Atlanta 2 – Phase 1 Atlanta 2 – Remaining Phases Suwanee DC 1 - Expansion
288 480 32
U/C In Planning - 2032 In Planning
QTS
STACK Infrastructure
Lithia Springs – Phase 1
87,890
12
U/C
KEEP - Expansion KEEP 2.0 – Phase 1
279,860 413,980
70 60
U/C In Planning – Q2 2026
Switch
Atlanta III – Phase 1 Atlanta III – Remaining Phases Atlanta IV
162,490 1,500,960 2,842,360 1,660,000
20 198 300
U/C In Planning In Planning In Planning
T5 Data Centers
Vantage Data Centers
Douglasville
96
*Excludes Captive & ICT construction updates.
†Total IT Load
ˆ RFS: Ready for Service
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW