Americas Data Center H2 2024 Update

TOR UNITED STATES

H2 24

SIGNIFICANT CONSTRUCTION & PLANNED UPDATES

OPERATOR

DATA CENTER

SIZE (SF)

POWER (MW)

STAGE - EST. DELIVERY

Toronto – Phase 2 Toronto – Phase 3

300,000 (est.) 300,000 (est.)

24 24

In Planning In Planning

STACK Infrastructure

CONTACTS Click on each name to send an email.

Equinix

TR6 - Expansion

24,000 (est.)

5.3 (est.)

U/C – Q2 2025

Etobicoke Woodbridge - Phase 1

279,800 244,000

84 56

U/C In Planning

Microsoft

RANDY BORRON Vice Chairman +1 (416) 359-2474 randy.borron@cushwake.com

DC4 DC5 – DC6

200,000 400,000

30 60

U/C In Planning

Urbacon

MICHAEL BORRON Associate Vice President +1 (416) 359-2481 michael.borron@cushwake.com

Yondr

Toronto

231,530

25 (est.)

In Planning

Updated

*Excludes Captive & ICT construction updates.

†Total IT Load

ˆ RFS: Ready for Service