Americas Data Center H2 2024 Update

RECENT PROPERTY SALES

CHI UNITED STATES

H2 24

SITE / PROPERTY

SIZE

SALE DATE SALE PRICE (US$) BUYER

SELLER

9375 Chestnut Ave, Franklin Park 1 acre

Dec-24

$3.4M

Digital Realty

Ricardo Martinez

E Devon Ave, Elk Grove Village

189,240 sf

Nov-24

$439.7M

HMC Capital

Prologis, Inc.

Eldamain & Faxon Rd, Yorkville

229 acres

Jul-24

$61M

CyrusOne

Green Door Capital LLC

2725 Bilter Rd, Aurora

32 acres

Jul-24

$16.8M

CyrusOne

Edged

CONTACTS Click on each name to send an email.

Busse Rd, Elk Grove Village

14 acres

Jul-24

$36.6M

EdgeConneX

Investcorp

400 S LaSalle St, Chicago**

298,000 sf

Jun-24

$12M

The Prime Group JV Capri Investment Group Cboe

ALEX SMITH Executive Vice Chair +1 (312) 470-3841 alex.smith@cushwake.com

30907 N Alleghany Rd, Grayscale 134 acres

May-24

$29.4M

T5 Data Centers

The Alter Group

SIGNIFICANT CONSTRUCTION & PLANNED UPDATES

STEPHEN SEVENICH Director +1 (312) 424-8905 stephen.sevenich@cushwake.com MICHAEL DUDERSTADT Director +1 (312) 424-8092 michael.duderstadt@cushwake.com

OPERATOR

DATA CENTER

SIZE (SF)

POWER (MW)

STAGE - EST. DELIVERY

1547 Critical Systems

CHIL1

230,000

25

In Planning

Updated

ORD03 ORD04

400,000 400,000

200 200

In Planning In Planning

Aligned Data Centers

CloudHQ

Arlington Heights Hoffman Estates

1,700,000

252

U/C & In Planning

Compass Datacenters

999,960

111

In Planning In Planning In Planning In Planning

Bensenville Yorkville Aurora

407,630 2,790,000 427,330

144 306 50

CyrusOne

EdgeConneX

CHI03

167,000

19

In Planning

CH3 CH4

252,000 252,000 565,000 414,000 538,190 1,614,580 330,000 248,000 TBD

36 36

In Planning In Planning In Planning In Planning U/C In Planning U/C - 2026 U/C In Planning In Planning In Planning

NTT

Cermak Franklin Park

54 30 (est.)

Digital Realty

Aurora 1 Aurora 2 & Aurora 3

24 72 36

Edged Energy

Iron Mountain

Des Plaines

Hoffman Estates – Phase 1 Plano

28 TBD

Microsoft

ORD01-02 ORD01-03

354,000 (est.) 354,000 (est.)

54 54

Prime Data Centers

*Excludes Captive & ICT construction updates.

†Total IT Load

ˆ RFS: Ready for Service

**Conversion

CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW

Made with FlippingBook Ebook Creator