Americas Data Center H2 2024 Update
Animated publication
AMERICAS DATA CENTER H2 2024 UPDATE
FEATURED IN THIS UPDATE
• PRIMARY MARKETS: Virginia, Atlanta, Phoenix, Chicago, Dallas, Columbus, Portland and Eastern Oregon, Silicon Valley
• SECONDARY MARKETS: Austin, Toronto, New Jersey and New York, Montreal, São Paulo, Bogotá, Querétaro, Santiago
H2 2024
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
H2 2024 UPDATE
AMERICAS DATA CENTER UPDATE – H2 2024 Artificial Intelligence (AI) continued to be a topic of interest to the data center industry in 2024, and demand for capacity has grown to reflect that interest over the course of the year. The construction pipeline swelled in the second half of the year, with 6.4GW of capacity underway — most of which has already been leased, as large-scale contiguous live capacity remains scarce. Power constraints remain the top challenge for hyperscale and colocation providers, heavily influencing site selection and driving expansion into less established data center markets across the region. Many regional utility providers have gigawatts of unfulfilled requests. Available space in operational data centers is scarce throughout the Americas, with just 607MW available across 569 facilities in North, Central and Latin America. Much of this space is 1MW or less, driving heightened leasing activity in the growing development pipeline. Of the 6.4GW currently under construction, 82% is already committed, with another 17% of planned capacity spoken for. The total planned data center pipeline has surged to 46GW, as demand for cloud computing and AI continues to accelerate. years or more. Where utility providers can't provide power sooner, some operators have collaborated with power companies to deliver substations, transmission lines or tap into microgrid power. Many of these agreements are being signed directly with third-party energy generation developers, accelerating wind, solar, battery storage, natural gas and geothermal projects. In markets like Atlanta and Silicon Valley, new power generation plans to ease constraints are being created or are newly in place. Meanwhile, a growing segment of hyperscale users is exploring the feasibility of implementing small modular reactors (SMRs) to meet power needs, though deployments of this technology are at least five years away. Hyperscale development in the Americas is largely driven by power availability first, with land values and availability second — spurring activity in periphery markets. Occupiers remain focused on availability and, unlike hyperscale users, are often bound to specific markets. Power availability remains the top consideration for data center developers, with operators seeking two- to three-year delivery times but often facing delays of five
North America continued its high-growth trajectory, reaching 20GW of operational capacity, with 1.5GW added in H2 2024, bringing the total capacity added for the year to 3.2GW.
With power and component lead times constraining delivery of new supply, vacancy region wide is currently at 4.9%, driving 82% of deliveries to be preleased and placing upward pressure on lease rates. Interest in large-scale power availabilities, plentiful land and less strict latency requirements for AI has driven hyperscalers and operators to expand into historically peripheral markets like Indianapolis, Kansas City, Reno, Charlotte, Salt Lake City, Minneapolis, Philadelphia, Montgomery, and other outlying areas.
Virginia remains the largest data center market globally, with 5.9GW in operation, 1.8GW under construction, and 15.4 GW planned. Following Virginia in operational capacity are other large markets: Portland and Eastern Oregon (2GW), Columbus (1.8GW), Phoenix (1.5GW), Dallas (1.4GW), and Chicago (1.2GW), all of which have seen continued activity
despite varying power availability limitations.
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
UNITED STATES
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
VIRGINIA AMERICAS PRIMARY MARKET
FREDERICK
ASHBURN + LEESBURG
KEY INDICATORS*
MANASSAS
CULPEPER
5,926MW In Operation
924MW 2024 Colo Leasing
FREDERICKSBURG
1,834MW Under Construction
1.5% Colo Vacancy
RICHMOND
Colo
*Definition: Key indicators are based on operational Hyperscale Cloud, Colo, Edge & Telco data centre facilities in the market and excludes Captive & ICT.
Hyperscale Self-build
MARKET OVERVIEW Virginia continues to see high levels of growth and tight market vacancy with limited availability in operational data centers. To satisfy their demand, occupiers are largely looking for data centers currently under construction or in the planning stages. Operators have remained bullish on the world’s largest data center market and continued their trend of expanding pipelines despite the many challenges surrounding land and power availability in the Virginia market. Currently, 1.8GW of capacity is under construction, with 89% preleased, while 15.4GW is in the planning stage, with 9% preleased. At 1.6%, vacancy is extremely tight, but it only partially explains the tightness of Virginia’s data center marke,t as it largely consists of small amounts of available capacity spread across numerous data centers. For example, the largest available capacity in a single operational data center in the entire state is 10.0MW, located in Richmond. Beyond that, only two operational data centers offer more than 5MW, while nine have between 1MW and 4.9MW available, and 31 have less than 1MW. Many occupiers currently in the market are looking for more contiguous capacity than the market can support, which is why their attention has turned to the development pipeline. Land constraints are another significant challenge, driving up land values and pushing transactions farther from the NoVA core. However, established submarkets, like Ashburn, still have available parcels. Operators seeking to capitalize on the submarket’s extensive data center infrastructure are paying over $4 million per acre. Despite the high cost, data center land transaction activity is still prominent throughout the state, even as power delivery timelines for new data centers extend beyond 2029. However, while there is a high degree of speculation activity for land between Fredericksburg and Richmond, land acquisitions in this area are currently hindered by labor constraints for transmission infrastructure upgrades needed for further data center development. Power constraints continue to be the norm in Virginia, as Dominion Energy, which supplies the area with power, has struggled to meet growing power demand from existing data centers and those currently under construction. However, long-term relief may come as nuclear power gains traction, the viability of small modular reactors becomes clearer, and Dominion strengthens its transmission network while advancing plans to increase generation and improve transmission infrastructure.
ECOSYSTEM DEVELOPMENTS
• Stack Infrastructure recently purchased 504 acres from Peterson Companies at the Stafford Technology Campus, becoming NoVA’s second-largest land deal. Peterson Companies had previously secured rezoning approval to allow the development of a hyperscale data center facility. Stack will build a data center for a hyperscale client on the site. • Yondr officially completed and launched its first data center on the company’s campus in Loudon County. The data center is 48MW in size, and an additional 48MW is currently underway as the second phase of construction began. • TPG Real Estate and Quantum Loophole separated and will no longer develop the Quantum Frederick Project as partners. TPG-owned Catellus Development corporation will be the sole developer of the project going forward. At full buildout, the 2,100-acre campus is planned to have 2GW of capacity. • Dominion Energy and Amazon entered a memorandum of understanding to explore nuclear energy development in Virginia with small modular reactors. This trend of using small modular reactors to power data centers is becoming more common nationwide as power constraints persist in many markets. • QTS made two land acquisitions totaling 928 acres, including a 620-acre site in Sandston and a 308-acre site just outside of Martinsburg, West Virginia. • Stack Infrastructure recently received zoning approval for their data center campus site in Gainesville. Once built, the campus will have 108MW of capacity and span 815 thousand square feet. Stack also recently expanded its presence in Loudon County with a 36-acre land acquisition in Leesburg. • Aligning with the trend of NoVA data centers expanding outward, Rowan Digital secured 151 acres of land in Frederick, Maryland, where it plans to build single-tenant data centers. • Amazon’s proposal for three new data centers was shelved indefinitely by the Prince William Board of County Supervisors, citing noise pollution, the concentration of existing data centers, and redevelopment plans. In other news, a company linked to Amazon, Minnieville Capital Acquisitions LLC , acquired 39 acres in Manassas. • Iron Mountain has been active across Virginia, recently acquiring 40 acres in Manassas for a two-building 150MW project. The company also filed to expand its Manassas campus on Wellington Road with the VA-8 facility and purchased 66 acres in Henrico County’s White Oak Technology Park, which will support more than 200MW of capacity.
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
RECENT SALES
NOVA UNITED STATES
H2 24
SITE / PROPERTY
SIZE
SALE DATE SALE PRICE (US$)
BUYER
SELLER
Jefferson Davis Hwy, Stafford
504 acres
Jan-25
$302.3M
Stack Infrastructure
Peterson Companies
Cosner Rd, Fredericksburg
30 acres
Dec-24
$4.8M
PowerHouse
Amazon
Arcola Blvd, Arcola
48 acres
Dec-24
$155M
Amazon
Soave Enterprises
6110 Technology Creek Dr, Sandston 66 acres
Nov-24
$8M
Iron Mountain
Henrico County
CONTACTS Click on each name to send an email.
7816-8122 Bethlehem Rd, Manassas
40 acres
Nov-24
$113.5M
Iron Mountain
PRP Real Estate
21529 Beaumeade Cir, Ashburn**
265,850 sf
Nov-24
$154.1M
CyrusOne
PowerHouse JV Harrison Street
1600 Digital Dr, Chester
104 acres Sep-24
$16.5M
PowerHouse
Cartograf
ANNE ROSENAU Managing Director +1 (703) 847-2765 anne.rosenau@cushwake.com BEN MANN Senior Director +1 (202) 266-1141 ben.mann@cushwake.com
Ruther Glen, VA
534 acres Jul-24
$8.2M
CleanArc Data Centers Mara Loving
15650 Nalles Mill Rd, Culpeper
121 acres
Jul-24
$60.4M
EdgeCore
Arroyo Investors
Ruther Glen, VA
97 acres
Jul-24
$7.3M
CleanArc Data Centers The Virginia Bazaar
SIGNIFICANT CONSTRUCTION & PLANNED UPDATES Updated OPERATOR DATA CENTER SIZE (SF)
POWER (MW)
STAGE - EST. DELIVERY
AWS
Multiple Sites Multiple Sites
22,130,000 (est.)
Undisclosed Undisclosed Undisclosed Undisclosed 72 72 54 127 (est.) 72 1,144 (est.) 233 (est.) 677 (est.) 440 (est.) 828 (est.)
U/C & In Planning U/C & In Planning
Microsoft
1,250,000 (est.)
Compass Datacenters & QTS
PW Digital Gateway
22,000,000
In Planning In Planning
Starwood Capital
Herndon
2,200,000 (est.) 5,839,000 (est.)
CloudHQ
Multiple Sites
U/C & In Planning
Gainesville – Building 1 Gainesville – Building 2 Gainesville – Building 3 Gainesville – Remaining Phases Kincora
483,000 288,000
U/C – 2025 U/C U/C In Planning In Planning
270,000 (est.) 1,260,000 (est.) 500,000
Corscale
Digital Realty
Multiple Sites
13,168,000 (est.)
U/C & In Planning
Culpeper Fredericksburg Multiple Sites Multiple Sites Multiple Sites
2,100,000 5,500,000
In Planning In Planning
Peterson Companies
NTT
2,548,000 (est.) 3,248,000 (est.) 5,979,000 (est.)
U/C & In Planning U/C & In Planning U/C & In Planning
CyrusOne
270 (est.)
PowerHouse Data Centers
1,190 (est.)
Rowan Digital Infrastructure (Quantum Loophole)
Frederick, MD
777,5000 (est.)
(Undisclosed)
In Planning
STACK Infrastructure
Multiple Sites
4,190,000 (est.)
782 (est.)
U/C & In Planning U/C & In Planning
Sabey Data Centers
Ashburn
383,700 (est.)
54 (est.)
The BlackChamber Group
Multiple Sites
3,100,000 (est.)
740 (est.)
In Planning
*Excludes Captive & ICT construction updates.
†Total IT Load
ˆ RFS: Ready for Service
**Powered Shell
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
ATLANTA AMERICAS PRIMARY MARKET
SUWANEE
ALPHARETTA
KEY INDICATORS*
716MW In Operation
895MW 2024 Colo Leasing
METRO ATLANTA
LITHIA SPRINGS
DOUGLASVILLE
1,078MW Under Construction
3.5% Colo Vacancy
EAST POINT
*Definition: Key indicators are based on operational Hyperscale Cloud, Colo, Edge & Telco data centre facilities in the market and excludes Captive & ICT.
ECOSYSTEM DEVELOPMENTS •
MARKET OVERVIEW All signs in the Atlanta data center market point to sustained heightened demand, as hyperscalers and colocation providers continue to expand their footprints. The largest amount of space currently available in an operational data center is 5MW, while the under-construction pipeline exceeds 1GW, and planned projects total more than 3GW. Without large availabilities, occupiers have turned to upcoming development to satisfy their need for capacity. Colocation data centers currently under construction are 89% preleased, and planned projects are 27% preleased — both figures leading the nation in terms of preleasing percentages for established data center markets. The Atlanta City Council recently passed new legislation limiting new data center development in Atlanta, primarily near the Beltline and within a half a mile of MARTA stations, as they desire residential development and green space in these areas. While this news excludes these sites from consideration for data center development, it is not expected to limit supply. Developers have increasingly looked to suburban Atlanta and beyond for large parcels of land suitable for multi-facility campuses — a trend that has continued in recent years as large infill sites become scarcer and infill land values appreciate. Hyperscalers and colocation providers looking to establish or grow their presence in the Atlanta or across Georgia benefit from several advantages. In line with the state’s business friendly stance, Georgia Power has been approved to bring an additional 1.4GW of power online from Plant Yates, Governor Kemp vetoed a bill that sought to pause data center tax exemptions, and a tax credit for upgrade and expansions to existing data centers remains in place.
Atlas Development LLC proposed a $17 billion, 13-building data center campus called Project Sail, to be built on 832 acres near Newnan, Georgia, adjacent to Welcome Sargent Road and Wagers Mill Road. If approved, the campus would cover 4.9 million sf and generate an expected $1.6 billion in annual tax revenue after its estimated 2036 completion. • Stream Data Centers is planning a major new campus outside Atlanta, which will include nine data center buildings and two substations. The campus will span approximately 1.34 msf and is expected to offer up to 280MW of power within 24 months of lease execution. This development marks Stream's first significant entry into the Atlanta market. • Northern Data Group is developing a state-of-the-art data center in Maysville, Georgia, to meet the growing demand for AI and High-Performance Computing (HPC) solutions. The facility will deliver 120MW initially in the first quarter of 2027, with the potential to expand to 180MW, The center is expected to support the local economy with the creation of up to 100 new jobs. • Edged Energy launched its first North American data center at 1800 Tilford Yard in Atlanta. The campus will feature three data centers, with the first now live, delivering 27MW of capacity and expected to reach 168MW at full build-out. • Data Core Innovations proposed the Rumble Technology Campus, a $1.2 billion data center project in Monroe County, Georgia. Spanning 900 acres between Forsyth and Macon, the campus will feature up to 12 buildings totaling 4.2 msf. The Monroe County board approved rezoning for the northern 525 acres from agriculture to commercial use. Construction is slated to start in late 2025 or early 2026, with the first building expected to launch in 2028.
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
RECENT SALES SITE / PROPERTY
ATL UNITED STATES
H2 24
SIZE
SALE DATE
SALE PRICE (US$) BUYER
SELLER
2525 Westside Pky, Alpharetta
240,226 sf
Dec-24
$40M
Lincoln Property Company DXC Technology Company
7800 Strickland St, Douglasville
129 acres
Nov-24
$64.7M
Amazon
TPA Group
2111 Powell Rd, Augusta
212 acres
Oct-24
$31.2M
QTS
Barbara W Sims
Veterans Pky, Fayetteville
204 acres
Sep-24
$39.8M
QTS
Huffman Group
2335 Echo Rd, Lithia Springs
119 acres
Sep-24
$37.1M
Amazon
Taylor & Mathis, Inc.
CONTACTS Click on each name to send an email.
Gullatt Rd, Palmetto
92 acres
Aug-24
$40.7M
T5 Data Centers
Red Rock Developments
2 Gene Allen Rd, Hampton
262 acres
Jul-24
$118M
Equinix
Powergrid Real Estate
151 Etowah Ridge Trl SE, Cartersville 29 acres
Jul-24
$0.3M
Switch
E T Properties Inc.
JOHN McWILLIAMS Head of Data Center Insights, Global Think Tank +1 (303) 312-4233 john.mcwilliams@cushwake.com
4830 Stonewall Tell Rd, College Park 65 acres
Jul-24
$318.5M
EdgeConneX
TA Realty
411 Pegasus Pky, Lagrange
268 acres
Jul-24
$50M
Thor Equities
Jindal Films Americas LLC
SIGNIFICANT CONSTRUCTION & PLANNED UPDATES
OPERATOR
DATA CENTER
SIZE (SF)
POWER (MW)
STAGE - EST. DELIVERY
ATL 4 ATL 5
387,500 968,750
40 120
U/C In Planning
DataBank
Douglasville – Phase 1 Douglasville – Remaining Phases Conyers
1,000,000 250,000 1,000,000 300,000 450,000 450,000 466,000 1,198,000 250,000 490,000 245,000 490,000 2,474,830 4,124,700 385,000
80 120 160 (est.)
U/C – Q4 2025 In Planning In Planning
DC Blox
Digital Realty
10 Forsyth
28
In Planning U/C In Planning
Tilford Yard – Phase 2 Tilford Yard – Remaining Phases
100 (est.) 41 (est.)
Edged Energy
Flexential
Douglasville – Phase 2
90,000 (est.)
13.5 43 265
U/C
Stanton Springs 2 – Phase 2 Stanton Spring 2 – Remaining Phases
U/C – 2026 In Planning U/C U/C U/C In Planning
Meta
Palmetto – Phase 1 Douglasville – Phase 1 East Point – Phase 1 Project Rita
26 40
Microsoft
57 (est) 96 (est)
Atlanta 2 – Phase 1 Atlanta 2 – Remaining Phases Suwanee DC 1 - Expansion
288 480 32
U/C In Planning - 2032 In Planning
QTS
STACK Infrastructure
Lithia Springs – Phase 1
87,890
12
U/C
KEEP - Expansion KEEP 2.0 – Phase 1
279,860 413,980
70 60
U/C In Planning – Q2 2026
Switch
Atlanta III – Phase 1 Atlanta III – Remaining Phases Atlanta IV
162,490 1,500,960 2,842,360 1,660,000
20 198 300
U/C In Planning In Planning In Planning
T5 Data Centers
Vantage Data Centers
Douglasville
96
*Excludes Captive & ICT construction updates.
†Total IT Load
ˆ RFS: Ready for Service
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
PHOENIX AMERICAS PRIMARY MARKET
GLENDALE
KEY INDICATORS*
1,541MW In Operation
669MW 2024 Colo Leasing
GOODYEAR
PHOENIX CBD
MESA
478MW Under Construction
2.5% Colo Vacancy
CHANDLER
Colo
Hyperscale Self-build
*Definition: Key indicators are based on operational Hyperscale Cloud, Colo, Edge & Telco data centre facilities in the market and excludes Captive & ICT.
MARKET OVERVIEW Demand for data center space in Phoenix has shown no sign of slowing down, with colocation leasing and preleasing activity increasing over the last three years. In 2022, the market saw a record 411MW in colocation leasing activity, which was topped by 643MW in 2023, and 669MW in 2024. Currently, the Phoenix colocation market has 24MW of available capacity, the largest block being 9MW. Like other established data center markets in the U.S., strong demand and limited availability have led wholesale occupiers looking to turn to planned and under-construction data centers to meet their needs, as reflected by the 84% prelease rate for data centers under construction across the Phoenix metro area. The planned pipeline signals years of development, with 4.7GW of capacity waiting to be built, 949MW of which is already committed. Vacancy in this market, at 2.5%, is very low, just like other high-performing established markets across the country. While it symbolizes the tightness of the market, it doesn’t fully capture how tight the market is for hyperscalers and wholesale colocation occupiers that often have needs that are larger than what is currently available. However, retail occupiers, which often have capacity needs that are less than 1MW, can still find space, with 12 data centers operated by well-known providers offering individual availabilities ranging from 200kW to 9.0MW. The Phoenix market’s appeal is bolstered by its proximity to Southern California, cost advantages over nearby markets, favorable Arizona incentives, low natural disaster risk, desert environment, and strong fiber infrastructure. These factors have led to the region’s 1.5GW of operational capacity and a healthy development pipeline. However, concerns about power demands and noise pollution have led cities like Mesa, Chandler and Phoenix to limit new development, resulting in increased land acquisition activity by hyperscalers and wholesalers in the western part of the metro, including Goodyear, Avondale, Peoria and El Mirage.
ECOSYSTEM DEVELOPMENTS •
Mesa, Chandler and Phoenix stopped inviting new data center developments due to concerns about power demands and noise pollution. As a result, new projects are focusing on the western suburbs like Peoria, El Mirage and Laveen Village, strengthening the Greater Phoenix area as a key data center hub. • Phoenix's power and water usage are under scrutiny due to high absorption rates, prompting SRP and APS to ask providers to run generators during peak usage times to prevent brownouts, despite concerns about ESG and PUE scores. • Land acquisition activity in the Phoenix market has surged in the second half of 2024, with notable transactions including Amazon’s purchase of 218 acres in Laveen Village, Aligned purchasing 95 acres in Peoria, QTS purchasing the 206-acre Hermosa Ranch Tech Campus in Avondale, and Compass Data Centers purchasing 121 acres in El Mirage. • Aypa Power secured a $398 million financing package for its 250MW/1,000MWh Pediment BESS project in Mesa, set to be operational in 2026, with Société Générale leading the financing and SRP committing to a 20-year tolling agreement. • Vantage recently held a toppin-out ceremony for its AZ14 data center in Goodyear, Arizona, which is part of a larger campus containing 176MW of capacity. In line with current trends, the facility has been 100% preleased since 2023. • Data center master plan developer Tract Group moved forward with purchasing a new 2,069-acre site for data center development in Buckeye, Arizona, after the developer withdrew its previous application to develop a smaller 1,400-acre site in Maricopa County. The new site will support up to 20 msf across 40 data center buildings, with Tract working with the local utility to secure 1.8GW to power the expansive site. The project is expected to be built out in multiple phases over the next 15 years, represents a $20 billion investment, and is expected to create 500 full-time jobs once complete.
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
RECENT SALES SITE / PROPERTY
PHX UNITED STATES
H2 24
SIZE
SALE DATE
SALE PRICE (US$) BUYER
SELLER
8785 N Reems Rd, Waddell
100 acres
Dec-24
$86.5M
Aligned Data Centers
LXP Industrial Trust
Loop 202 & Dobbins Rd, Laveen
229 acres
Oct-24
$277.3M
Amazon
IDM Companies
75th Ave & Northern Ave, Glendale
19 acres
Oct-24
$10.2M
Aligned Data Centers
Renewal Mgmt. Remainder Trust
7823 W Seldon Ln, Peoria
78 acres
Sep-24
$42.2M
Aligned Data Centers
VanTrust Real Estate LLC
CONTACTS
S Johnson Rd, Buckeye
2,069 acres Aug-24
$136.1M
Tract
Cirpriani Holdings LLC
Click on each name to send an email.
11753 W, Tolleson
206 acres
Jul-24
$246.9M
QTS
TGV Investments Group
DON RODIE Managing Director
20435 N 26th Ave, Phoenix
54,655 sf
Jul-24
$12M
Paycom
Safeway Inc.
+1 (602) 229-5918 x305918 don.rodie@cushwake.com
SIGNIFICANT CONSTRUCTION & PLANNED UPDATES
OPERATOR
DATA CENTER
SIZE (SF)
POWER (MW)
STAGE - EST. DELIVERY
JOHN McWILLIAMS Head of Data Center Insights, Global Think Tank +1 (303) 312-4233 john.mcwilliams@cushwake.com
5C Data Centers
PHX01
140,000 452,000 452,000 624,000 289,000 84,000
20
In Planning In Planning In Planning In Planning
Elliot Rd, Mesa Pecos Rd, Mesa
Undisclosed Undisclosed
AWS
Updated
Compass Datacenters
PHX II
108
Redhawk, Mesa – Phase 1 Redhawk, Mesa – Phase 2
12 18
U/C – Q3 2025 In Planning U/C & In Planning U/C & In Planning U/C & In Planning In Planning
Meta
Mesa – Phase 2+
2,150,000 (est.)
300 (est.)
NTT
Phoenix – Remaining Phases PHX2 – Remaining Phases Glendale
1,524,000
204
1,349,000 5,812,000 (est.) 398,300 (est.) 452,000 (est.) 450,000 (est.)
144 (est.) 768 (est.) 108 (est.) 72 (est.) 72 (est.)
QTS
PHX-06 PHX-07 PHX-08
In Planning U/C – 2025 In Planning In Planning In Planning
Aligned Data Centers
Downtown Phoenix Goodyear
833,900 1,784,000
246 176
STACK Infrastructure
PhoenixNAP
Phoenix
500,000
30
In Planning – Q4 2026
AZ14 & AZ15 AZ2
512,000 (est.) 432,000 (est.) 1,475,000 (est.) 1,162,000 (est.)
112 (est.) 48 (est.) 132 (est.)
U/C & In Planning In Planned
Vantage Data Centers
EdgeCore
Mesa – Phase 2
U/C - 2025 In Planning U/C In Planning
EdgeConnex
Mesa
100 40 160
PHX II PHX III – PHX VI
418,200 2,091,000
Stream Data Centers
Avondale – Phase 1 Avondale – Remaining Phases
260,000 1,042,000 (est.)
7 233 (est.)
U/C – Q4 2025 In Planning
Prime Data Centers
*Excludes Captive & ICT construction updates.
†Total IT Load
ˆ RFS: Ready for Service
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
CHICAGO AMERICAS PRIMARY MARKET
HOFFMAN ESTATES
ELK GROVE VILLAGE
Colo
Hyperscale Self-build
KEY INDICATORS*
NORTHLAKE
DOWNTOWN CHICAGO
1,159MW In Operation
471MW 2024 Colo Leasing
AURORA
169MW Under Construction
5.4% Colo Vacancy
*Definition: Key indicators are based on operational Hyperscale Cloud, Colo, Edge & Telco data centre facilities in the market and excludes Captive & ICT.
MARKET OVERVIEW Like other established U.S. markets, demand for data center space has been rising in Chicago. Data center leasing activity in 2024 totaled 471MW for the year — a 257% increase over the 132MW leased in 2023, most of which occurred in data centers that are either planned or under construction. While colocation availability in Chicago, at 49MW, is greater than in other established markets, it is still limited, and most available space isn’t suitable for large-scale applications. Competition for land has continued in Chicago, particularly in Elk Grove Village near the O’Hare industrial corridor. This competition for available parcels is pushing buyers toward brownfield development if they wish to stay within the metropolitan area or outside of Chicago for larger greenfield parcels. Limited land availability, power constraints and Illinois’ Biometric Information Privacy Act (BIPA) is prohibiting further growth, which has caused an explosion of growth in northwestern Indiana, extending into southeastern Michigan. To attract Illinois’ demand, Michigan passed a data center sales tax abatement incentive. However, not all demand is leaving the state — land acquisitions in Illinois have been increasing outside the Chicago MSA. Microsoft, CyrusOne, Equinix and Aligned have all made sizeable land acquisitions along the westbound I-80 corridor. Iowa, much like northwestern Indiana and Michigan, has also seen growing interest, particularly in the Quad Cities area. Nevertheless, Chicago has continued to attract hyperscale users and colocation providers, and the planned capacity pipeline continues to grow as these groups seek out and acquire land suitable for data center development. Currently, 2.6GW of data center capacity rests in the planned pipeline and 7% has already been leased by data center users that wish to be in the Chicago market. Much of the planned development is concentrated in Elk Grove Village, which represents more than a 1GW of planned capacity, but planned development is also high in Hoffman Estates and Aurora.
ECOSYSTEM DEVELOPMENTS •
QTS received approval to construct a second data center on their Ashland Ave. campus, which has the potential to scale up to 125MW. The approval required an amendment to QTS’ original development plans. • Midcontinent Independent System Operator (MISO) approved a $21.9 billion long-range transmission plan, with projects expected to come online from 2032 to 2034. The plan includes a 765kV transmission backbone across the Midwest, designed to enhance power flow, improve reliability, and support new data centers and industries. • Power availability and grid infrastructure remain significant obstacles for new data center development. Current power delivery estimates for new data centers under 50MW could reach 18-24 months, while larger projects may not be able to secure the necessary power until 2028 or 2029. • Demolition is underway at the former Sears campus in Hoffman Estates, where Compass Datacenters plans to develop a five-building data center campus. Construction on the 200-acre site is expected to begin in 2025. • Microsoft acquired 506 acres across multiple parcels in Plano, Illinois, west of Chicago. The property was recently annexed into Plano by the city council and rezoned for data center development. • The Chicago City Council approved the Chicago Data Residency Ordinance, which took effect January 1, 2025. The ordinance provides financial incentives for data centers built in the city, but developers must address power delivery solutions, as distribution lines and substations needed for new data centers are lacking.
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
RECENT PROPERTY SALES
CHI UNITED STATES
H2 24
SITE / PROPERTY
SIZE
SALE DATE SALE PRICE (US$) BUYER
SELLER
9375 Chestnut Ave, Franklin Park 1 acre
Dec-24
$3.4M
Digital Realty
Ricardo Martinez
E Devon Ave, Elk Grove Village
189,240 sf
Nov-24
$439.7M
HMC Capital
Prologis, Inc.
Eldamain & Faxon Rd, Yorkville
229 acres
Jul-24
$61M
CyrusOne
Green Door Capital LLC
2725 Bilter Rd, Aurora
32 acres
Jul-24
$16.8M
CyrusOne
Edged
CONTACTS Click on each name to send an email.
Busse Rd, Elk Grove Village
14 acres
Jul-24
$36.6M
EdgeConneX
Investcorp
400 S LaSalle St, Chicago**
298,000 sf
Jun-24
$12M
The Prime Group JV Capri Investment Group Cboe
ALEX SMITH Executive Vice Chair +1 (312) 470-3841 alex.smith@cushwake.com
30907 N Alleghany Rd, Grayscale 134 acres
May-24
$29.4M
T5 Data Centers
The Alter Group
SIGNIFICANT CONSTRUCTION & PLANNED UPDATES
STEPHEN SEVENICH Director +1 (312) 424-8905 stephen.sevenich@cushwake.com MICHAEL DUDERSTADT Director +1 (312) 424-8092 michael.duderstadt@cushwake.com
OPERATOR
DATA CENTER
SIZE (SF)
POWER (MW)
STAGE - EST. DELIVERY
1547 Critical Systems
CHIL1
230,000
25
In Planning
Updated
ORD03 ORD04
400,000 400,000
200 200
In Planning In Planning
Aligned Data Centers
CloudHQ
Arlington Heights Hoffman Estates
1,700,000
252
U/C & In Planning
Compass Datacenters
999,960
111
In Planning In Planning In Planning In Planning
Bensenville Yorkville Aurora
407,630 2,790,000 427,330
144 306 50
CyrusOne
EdgeConneX
CHI03
167,000
19
In Planning
CH3 CH4
252,000 252,000 565,000 414,000 538,190 1,614,580 330,000 248,000 TBD
36 36
In Planning In Planning In Planning In Planning U/C In Planning U/C - 2026 U/C In Planning In Planning In Planning
NTT
Cermak Franklin Park
54 30 (est.)
Digital Realty
Aurora 1 Aurora 2 & Aurora 3
24 72 36
Edged Energy
Iron Mountain
Des Plaines
Hoffman Estates – Phase 1 Plano
28 TBD
Microsoft
ORD01-02 ORD01-03
354,000 (est.) 354,000 (est.)
54 54
Prime Data Centers
*Excludes Captive & ICT construction updates.
†Total IT Load
ˆ RFS: Ready for Service
**Conversion
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
DALLAS AMERICAS PRIMARY MARKET
PLANO
FORT WORTH
GARLAND
RICHARDSON
KEY INDICATORS*
1,368MW In Operation
454MW 2024 Colo Leasing
500MW Under Construction
6.4% Colo Vacancy
SOUTH DALLAS
Colo
*Definition: Key indicators are based on operational Hyperscale Cloud, Colo, Edge & Telco data centre facilities in the market and excludes Captive & ICT.
Hyperscale Self-build
MARKET OVERVIEW Leasing activity in Dallas totaled 454MW in 2024, slightly below the 478MW leased in 2023 but still significantly higher than pre-2023 levels. Despite strong leasing activity, colocation availability in Dallas, is still higher than many other established markets — including Virginia — with 72MW of capacity on the market. Vacancy rates reflect this level of availability and currently sit at 6.4% across the metroplex. Of nearly 100 operational data centers in the Dallas market, 38 have some level of availability, though much of it is 1MW or less. Despite the 6.4% vacancy rate, demand in Dallas is showing no sign of letting up, particularly along the I-35 corridor to the south. The under-construction pipeline currently tops 500MW, with 88% preleased, while planned developments now surpass 4GW as well-known colocation firms commit to the market. The composition of the market is changing as well, further positioning Dallas as a major data center market, as wholesale providers represent a significant portion of the pipeline. Though hyperscale self-builds are represented in current operational commissioned capacity figures, they are largely absent from the pipeline, as hyperscalers either lease wholesale space or have otherwise shown more interest along the I-35 corridor between Dallas-Fort Worth and Austin, or farther west toward Abilene. This shift is driven by rising land values in the metroplex and growing concerns over long-term power availability. It is important to note that power availability is less constrained in Dallas than it is in other established markets, and power timelines are often shorter. Also, utility providers in the Dallas area are actively planning to accommodate rising power needs. For example, ERCOT’s regional transmission plan, covering 2026 to 2030, outlines investments in new transmission lines and substations to ease power delivery concerns. Additionally, the U.S. Department of Energy announced $1.5 billion to increase ERCOT’s grid reliability by connecting it to southeastern power markets.
ECOSYSTEM DEVELOPMENTS •
ERCOT's latest Regional Transmission Plan, released in December, includes upgrades to kV lines and new substations slated for 2026 to 2030. A joint study with Oncor, expected in 2025, will evaluate south Dallas, potentially shaping future investments in the area. • The Department of Energy (DOE) will provide $1.5 billion for four electrical transmission projects, including the 320-mile Southern Spirit line connecting ERCOT to southeastern power markets. This project aims to enhance grid reliability in Texas, which relies heavily on the ERCOT grid. • Rpower and Wise Asset are partnering to offer natural gas-powered land solutions for data center developers in Texas. They plan to develop over 3,000 acres in the Dallas-Fort Worth area to meet the growing demand for energy from large users, with availability by 2027. • CyrusOne plans to build a $200-million data center in Fort Worth, which is expected to be completed by the first quarter of 2026. This will be the company’s 15th facility in the state, adding to their extensive portfolio of data centers across the U.S. and globally. The facility, dubbed DFW7, will be located at Asphalt Drive in Fort Worth, Tarrant County, and will span 1.9 msf across a one-story data center and a two-story office component. • DataBank announced the development of a 480MW data center campus on 292 acres in Red Oak, Texas. The campus will feature up to eight two-story data centers, adding to DataBank's significant presence in the Dallas area. Phase 1, expected to be completed by the second quarter of 2026, will include four buildings and a 400MW substation from Oncor that will deliver up to 240MW of critical IT power. Phase 2 will expand this capacity to a total of 480MW across all eight buildings. • Hanwha Energy plans to develop a 200MW AI data center in Texas, estimated to cost $1.45 billion. Construction is set to begin next year, pending necessary power and water infrastructure, with the data center expected to operate hundreds of thousands of servers and be partially powered by Hanwha's 2GW solar plant in Texas.
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
RECENT PROPERTY SALES
DFW UNITED STATES
H2 24
SITE / PROPERTY
SIZE
SALE DATE
SALE PRICE (US$)
BUYER
SELLER
1402 E Lookout Dr, Richardson**
129,200 sf
Dec-24
$98M
DigiCo Infrastructure REIT JDM Partners
1201 N Bowser Rd, Richardson
7 acres
Oct-24
$15M
Digital Realty
Halff
CONTACTS
Click on each name to send an email.
SIGNIFICANT CONSTRUCTION & PLANNED UPDATES
BO BOND Executive Managing Director 1 +1 (972) 663-9749 bo.bond@cushwake.com ALI GREENWOOD Executive Director +1 (972) 663-9750 ali.greenwood@cushwake.com
OPERATOR
DATA CENTER
SIZE (SF)
POWER (MW)
STAGE - EST. DELIVERY
Compass Datacenters
Red Oak VI – Red Oak X 1,000,000
180 (est.)
U/C
Aligned Data Centers
DFW03
429,600
72 (est.)
U/C & In Planning – Q1 2026
DataBank
DFW9
425,200
60
U/C - 2027
Updated
Irving – Remaining Phases FTW DC2
1,500,000 (est.) 471,880
108 (est.) 42
U/C & In Planning U/C
QTS
Equinix
DA12
(Undisclosed)
150 (est.)
In Planning
RICK HUGHES Executive Managing Director +1 (972) 663-9601 rick.hughes@cushwake.com
Digital Realty
Garland – Expansion
410,000
42
In Planning – Q4 2026
NTT
TX4
139,500(est.)
15
In Planning - 2026
Irving – Phase 1 Irving – Remaining Phases
315,340 630,670
67 134
In Planning – Q1 2026 In Planning In Planning – Q1 2026 In Planning In Planning U/C - 2027 In Planning – 2026
PowerHouse Data Centers
Fort Worth – Phase 1 Garland – Phase 1 Dallas DFW01C – Phase 1 Lancaster DFW VIII DFW IX – DFW X Lancaster – Phase 1 Red Oak
267,000 534,000 (est) 96,800
48 96 (est) 12
Prime Data Centers
436,000 1,500,000
12 220
STACK Infrastructure
135,290 270,580
30 60
U/C In Planning U/C - 2026 In Planning
Stream Data Centers
270,900 750,000 (est)
48 (est) 125
Skybox, Bandera Ventures
*Excludes Captive & ICT construction updates.
†Total IT Load
ˆ RFS: Ready for Service
**Part of a portfolio transaction
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
PORTLAND + EASTERN OREGON AMERICAS PRIMARY MARKET
HILLSBORO
THE DALLES
PORTLAND CBD
UMATILLA
KEY INDICATORS*
1,970MW In Operation
33MW 2024 Colo Leasing
236MW Under Construction
0.5% Colo Vacancy
PRINEVILLE
Colo
Hyperscale Self-build
*Definition: Key indicators are based on operational Hyperscale Cloud, Colo, Edge & Telco data centre facilities in the market and excludes Captive & ICT.
ECOSYSTEM DEVELOPMENTS •
MARKET OVERVIEW Demand remains strong in Portland and Eastern Oregon, as indicated by an extremely tight vacancy rate of 0.5%. Though this market is primarily driven by hyperscale self-builds, the colocation market — at 535MW — is expected to double in the coming years. The current pipeline reflects this growth, with 730MW of colocation capacity in the planning stages, led by QTS, Aligned Data Centers and Stack Infrastructure. However, warnings of power constraints are materializing, contributing to the less colocation space currently under construction and the expanding planned colocation development pipeline. In response, PacifiCorp has introduced new power usage penalty rules for large-load customers in the Pacific Northwest, effective February 2025. These rules penalize users who deviate from their initially projected or requested power needs. Despite Oregon’s power challenges, demand drivers such as renewable energy, more affordable land prices, and proximity to west coast markets have continued to attract hyperscale and colocation providers. Power purchase agreements (PPAs) are still being signed, albeit to a lesser extent, despite concerns surrounding power availability and use. Both QTS and Meta recently entered a PPA with Avangrid and Portland General Electric for a 120MW solar energy project in Morrow County. With incentives like renewable energy, strong network connectivity, a resilient tech workforce and lower power cost, the market is primed for continued growth. However, new entrants to the market should be aware of increasing regulatory pushback to new data center developments, further highlighting the importance of sustainable construction and energy usage that benefit local communities. Significant opportunities remain for growth in the data center market across the state.
The Pacific Northwest Utilities Conference Committee ( PNUCC) projects a significant surge in electricity demand in the region, with an annual growth rate of 3.1% over the next decade, driven by the expansion of data centers and high-tech manufacturing. To meet this demand, utility providers plan to add 29GW of new capacity, and demand response programs are expected to double. • Avangrid and Portland General Electric (PGE) signed a PPA with QTS and Meta for a 120MW solar energy project in Morrow County, Oregon. The Tower Solar project will supply renewable energy to a new QTS data center campus supporting Meta's operations. It is expected to be operational by 2026 • PacifiCorp's new power usage penalty rules, approved by the Oregon Public Utility Commission, will take effect in February 2025. These rules penalize large-load customers, such as data centers, for deviating from their projected power needs. PacifiCorp aims to extend these rules to Utah and Washington • Aligned Data Centers topped out its PDX-01 data center in Hillsboro, Oregon. The 72MW facility, featuring a dozen 6MW data halls across 27 acres, will offer 100% renewable energy options and support air, liquid or hybrid cooling solutions. A second planned building, PDX-02, will add an additional 36MW of IT capacity.
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
PDX UNITED STATES
H2 24
SIGNIFICANT CONSTRUCTION & PLANNED UPDATES
OPERATOR
DATA CENTER
SIZE (SF)
POWER (MW)
STAGE - EST. DELIVERY
CONTACTS Click on each name to send an email.
AWS
NE Oregon (Multiple Sites)
3,519,000 (est.)
384 (est.)
U/C & In Planning
NTT
Hillsboro Campus – Expansion
193,750 (est.)
78
U/C & In Planning
JOHN McWILLIAMS Head of Data Center Insights, Global Think Tank +1 (303) 312-4233 john.mcwilliams@cushwake.com
Digital Realty
Portland 3 – Expansion
68,900 (est.)
8
U/C
Forest Grove – Phase 1 Forest Grove – Phase 2 POR02 – Expansion POR03 Umatilla – Phase 1 Umatilla – Phase 2+ POR01 – Expansion POR03 – Phase 2 POR03 – Phase 3+
600,620 600,620 8,300 229,300
50 50
In Planning In Planning In Planning In Planning In Planning In Planning In Planning U/C In Planning
Crane Data Centers
2 (est.) 19 (est.)
EdgeConneX
Updated 285,800 428,700
60 90
Sabey Data Centers
130,670 51,670 836,300
9 (est.) 12 120
STACK Infrastructure
Flexential
Hillsboro 5
323,000
36
U/C
1547 Critical Systems
Pittock Block - Expansion
57,000 (est.)
14
In Planning
Aligned Data Centers
Hillsboro – Phase 2
155,000 (est.)
36
In Planning
Rowan Digital Infrastructure
Percheron
1,406,250
196
In Planning
*Excludes Captive & ICT construction updates.
†Total IT Load
ˆ RFS: Ready for Service
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
SILICON VALLEY AMERICAS PRIMARY MARKET
SAN FRANCISCO
OAKLAND
KEY INDICATORS*
956MW In Operation
36.5MW 2024 Colo Leasing
FREMONT / NEWARK
39MW Under Construction
5.8% Colo Vacancy
SANTA CLARA
SAN JOSE
*Definition: Key indicators are based on operational Hyperscale Cloud, Colo, Edge & Telco data centre facilities in the market and excludes Captive & ICT.
Colo
Hyperscale Self-build
MARKET OVERVIEW Silicon Valley, and the broader Bay Area continue to see modest demand for data centers and consistent growth. Power constraints, expensive land and, to a lesser extent, seismic activity risks have kept the under-construction pipeline on a downward trend, with data center completions outpacing projects that have secured power and begun construction. As a result, the planned pipeline has grown to more than 1GW, while 39MW of colocation currently remains under construction. Demand for space in this market still exists, but instead of being able to meet that demand, it has once again radiated outward to nearby markets like Reno, Portland and Eastern Oregon, and Phoenix. However, this hasn’t stopped data center providers from requesting power from Pacific Gas & Electric (PG&E). In PG&E’s 2024 investor update, the company reported 3.5GW of new power requests from data center providers, with delivery dates extending through 2029. Some of these requests are substantial, including one customer seeking 600MW and 800MW. In response, PG&E has reinforced its commitment to the Bay Area’s energy needs by securing a $15 billion loan for infrastructure improvements, increased hydropower generation, expanded transmission capacity, and battery energy storage capacity. Meanwhile, Silicon Valley Power has encouraged new data center proposals to incorporate alternative energy or in-city generation. Will Silicon Valley and the Bay Area see a data center renaissance? It’s possible, but an improved grid and increased power generation won’t alleviate rising land values or provide immediate electricity rate relief. For that reason alone, Washington, Oregon, Nevada and Arizona will continue to offer a significant development and operational cost advantage over Silicon Valley.
ECOSYSTEM DEVELOPMENTS •
PG&E secured a $15 billion loan guarantee from the U.S. Department of Energy’s Loan Programs Office for Project Polaris. This funding will support the expansion of hydropower generation, battery storage and transmission capacity upgrades, helping PG&E meet future energy demands, improve reliability, and reduce costs for its 16 million customers in northern and central California. • Silicon Valley Power is leading efforts to address the increased energy demand from AI adoption by advocating for in-city generation or alternative energy sources in new data center proposals. AWS agreed to use natural gas-powered fuel cells from Bloom Energy at its Santa Clara data center, while Google partnered with Kairos Power to deploy 500MW of small modular reactors (SMRs) by 2035, with the first expected to be operational by 2030. • AWS plans a 15-year, 20MW power purchase agreement with Bloom Energy to support its new Silicon Valley data center, addressing the region's growing energy demands. The deal, expected to cost around $35 million in the first year, highlights AWS's commitment to meeting energy needs despite higher costs and environmental challenges. • GI Partners secured planning permission to build a 72MW data center at 2805 Bowers Ave. in Santa Clara, after the city council's unanimous approval. The project involves demolishing existing office buildings and constructing a new four-story data center, expected to be operational by 2029 or 2030.
CUSHMAN & WAKEFIELD | AMERICAS DATA CENTER MARKET OVERVIEW
Made with FlippingBook Ebook Creator