2025 DFW Market Update & 2024 Year In Review

TEAM MARKET INSIGHT

OFFICE SPACE CONSTRUCTION How long does it take to build a new office? This is a common quest and size of the space, as well as the city and permitting requirement Beyond the buildout itself, it’s important to account for the time recommended construction timeline to guide your office space eval

FULL TENANT BUILDOUT FROM SHELL CONDITION

Space Planning 2 Weeks

Schematic Design 2 Weeks

Design Development 2 Weeks

Construction Drawings 1 Month

Permit 1 Month

MODERATE RENOVATION OF 2ND GENERATION SPACE

Construction Drawings 1 Month

Space Planning 1 Week

Schem Design 1 Week

Design Dev 1 Week

Permit 1 Month

Constru 2-3 Mo

LIGHT RENOVATION

Tech & FF&E Install 2 Weeks

TOTAL 2-3 Month

Construction Drawings 3 Weeks

Space Planning 1 Week

Schem Design 1 Week

Design Dev 1 Week

Construction 1 Month

^

^

^

Begin